NextDecade, Occidental unit join forces on CO2 transport from Rio Grande LNG

US liquefaction plant developer NextDecade is teaming up with a unit of Occidental Petroleum for the offtake and storage of carbon dioxide captured from the proposed Rio Grande LNG export plant in Texas.

Under the term sheet, Oxy Low Carbon Ventures would offtake and transport CO2 from the LNG project and permanently sequester it in an underground geologic formation in the Rio Grande Valley, where there is vast CO2 storage capacity, NextDecade said.

NextDecade’s chief executive Matt Schatzman said the firm would work with OLCV to design, construct, and operate a CO2 pipeline and permanent storage facility in South Texas.

“OLCV’s expertise and reliability complement the transformative and impactful contributions our NEXT Carbon Solutions business is making to the global energy industry, and in particular the proprietary processes we are advancing to lower the cost of utilizing CCS technology,” he said.

The new move follows last week’s announcement by the US firm on launching a new unit to develop a carbon capture and storage project at the proposed LNG export plant in Texas.

NEXT Carbon Solutions’ CCS project could reduce permitted CO2 emissions at Rio Grande LNG by more than 90 percent without major design changes to the facility, according to NextDecade.

Announcing a “pricing refresh” deal with engineering giant Bechtel earlier this month, NextDecade said it anticipates achieving a final decision on a “minimum of two trains” at Rio Grande LNG this year.

NextDecade said it would also take a FID on the CCS project after that.

The full-scope of the Rio Grande project includes five trains for a total capacity of 27 million tonnes per year.

Most Popular

Cedar FLNG launched in South Korea

South Korea’s Samsung Heavy Industries has launched Cedar LNG's floating LNG production unit, which will be installed in Kitimat on Canada’s West Coast.

India’s Petronet LNG declares force majeure to offtakers

India's largest LNG importer has declared force majeure to its offtakers after it received a notice from state-owned QatarEnergy, which on Monday stopped production at its giant Ras Laffan LNG plant due to attacks.

BP submits lowest bid in Pakistan LNG tender

A unit of UK-based energy giant BP has submitted the lowest bid in a tender to supply Pakistan with one spot LNG shipment this week.

More News Like This

NextDecade appoints new finance chief

US LNG developer NextDecade has appointed John Zuklic as the company’s new chief financial officer, effective July 6.

NextDecade seeks FERC OK for sixth Rio Grande LNG train

US LNG developer NextDecade is seeking approval from the Federal Energy Regulatory Commission to build and operate the sixth liquefaction train and an additional marine berth at its Rio Grande LNG terminal in the Port of Brownsville, Texas.

NextDecade’s Rio Grande LNG secures FERC extension

NextDecade's Rio Grande LNG has secured a three-year extension from the US FERC to complete construction and place into service five trains at its LNG export plant in Texas.

NextDecade to charter more vessels to ship Rio Grande LNG volumes

US LNG developer NextDecade expects to charter more LNG carriers to ship volumes from its Rio Grande LNG terminal in Texas, while the company is also expecting to take a final investment decision on the sixth train in the second half of next year, according to Matt Schatzman, NextDecade chairman and CEO.