Pieridae, Uniper extend Goldboro LNG deadlines

Canada’s Pieridae Energy, the developer of the Golboro LNG export project, has negotiated extensions of the key deadlines under its long-term deal with Germany’s Uniper.

This development follows Pieridae’s announcement in April on postponing a final investment decision to build the Goldboro LNG export plant in Nova Scotia due to the effects of the coronavirus pandemic.

Pieridae has a 20-year agreement with German utility Uniper for all of the volumes from the first Goldboro liquefaction train.

The first train will have a capacity of or 4.8 million tonnes per year.

Under the newly negotiated deadlines, Pieridae will start commercial LNG deliveries to Uniper between August 31st, 2025 and February 28th, 2026.

Previously, Pieridae expected to start deliveries between November 30, 2024 and May 31, 2025.

The new deal also includes an extension to June 30, 2021 of the deadline to make a positive final investment decision for the Goldboro LNG facility.

Pieridae Energy previously expected to take a decision to build the $10 billion project in the third quarter of 2020 and start producing LNG between November 2024 and May 2025.

“Our relationship with Uniper remains strong and we very much appreciate their on-going support,” said Pieridae chief executive Alfred Sorensen.

LNG site preparation works to start

Sorensen said that Pieridae remains focused on progressing work with KBR to deliver a fixed price contract to build the gas liquefaction facility

Pieridae has begun to contract for services outside the primary engineering, procurement and construction contract with the intent to begin the site preparation work as soon as possible.

Some of these activities include building the wharf and jetty, road reconstruction, and constructing the work camp, Sorensen said.

The Goldboro LNG facility will have two trains with a combined production capacity of 9.6 million tonnes per year.

The construction of the facility will take about 56 months, according to Pieridae.

Most Popular

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

Glencore pens Chinese LNG supply deal

Switzerland-based energy trader Glencore has signed a long-term deal to supply liquefied natural gas (LNG) to a unit of China Suntien Green Energy.

Equinor seals long-term LNG SPA with Thailand’s PTT

Norwegian energy firm Equinor has signed a long-term LNG sales and purchase agreement with a unit of Thailand’s PTT.

More News Like This

Uniper, Equinor seal long-term gas supply deal

German energy and LNG firm Uniper has signed a long-term deal with Norway's Equinor for the supply of natural gas to Germany.

Uniper, Ksi Lisims LNG seal long-term LNG supply deal

German energy firm Uniper has signed a 20-year LNG sale and purchase agreement with Ksi Lisims LNG for volumes from the latter’s planned export project in Canada.

Uniper, Q1 Energie seal bio-LNG deal

German energy firm Uniper has signed a deal with compatriot Q1 Energie to supply its network of LNG truck filling stations in Germany with bio-LNG from the Dutch Gate terminal in Rotterdam.

Uniper, GSPC seal long-term LNG supply deal

German energy firm Uniper has signed a long-term deal with India's Gujarat State Petroleum (GSPC) to supply the latter with liquefied natural gas (LNG).