Tellurian, Baker Hughes ink Driftwood LNG equipment deal

US LNG terminal developer Tellurian has signed a deal with compatriot energy services firm Baker Hughes for the supply of eight main refrigerant compression packages for its Driftwood LNG project in Louisiana.

Tellurian CEO Octavio Simoes and Baker Hughes chairman and CEO Lorenzo Simonelli signed the equipment agreement during the second day of Gastech in Singapore.

The two firm said that the agreement secures a delivery schedule for the eight LM6000PF+ gas turbines, main refrigerant compressors, and control units required for the first Driftwood phase of, supporting Driftwood’s ability to achieve initial LNG production in 2027.

Baker Hughes is also on schedule to complete, by early next year, fabrication of the electric-powered integrated compressor line (ICL) packages and other turbomachinery equipment for Driftwood Pipeline 200, following the award in 2022.

Tellurian president and CEO Octavio Simoes said, “Bechtel has done a tremendous job preparing the site and has already completed the piling and compressor foundations for Plant 1 of Driftwood LNG.”

“This agreement with Baker Hughes firms up our plans to secure the critical technology for Driftwood Phase 1,” he said.

Tellurian CEO Octavio Simoes and Baker Hughes chairman and CEO Lorenzo Simonelli (Image: Tellurian)

Under the first phase, Tellurian aims to build two LNG plants near Lake Charles with an export capacity of up to 11 mtpa.

Last month, Tellurian’s co-founder and executive chairman, Charif Souki, said that Tellurian was working with Baker Hughes to secure long-lead items for its Driftwood LNG project, while engineering and construction giant Bechtel continues to progress initial work at the site in Louisiana.

Souki said that Tellurian has spent up to date $16 million dollars securing the turbine purchases and will continue to work with Baker Hughes for these deliveries.

“So look for more news on that,” he said last month.

“When we finalize this, we will have spent $1.5 billion on Driftwood to prepare it for the final notice to proceed,” he said.

Tellurian has not yet announced a final investment decision on the Driftwood first phase and the company is still working to secure financing for the project worth about $14.5 billion.

The company’s latest corporate presentation posted on its website shows the Driftwood capital structure includes $7 billion bank debt, $2 billion lease/mezzanine financing, $1.8 billion partner equity, $1.5 billion Tellurian equity, and also $2.5 billion contingent equity.

If the six months of commissioning LNG cargoes cover the contingent equity, the contingent equity will not be funded, according to Tellurian.

Most Popular

Cheniere produces first LNG cargo at Corpus Christi expansion project

US LNG exporting giant Cheniere has produced the first cargo at the Corpus Christi Stage 3 expansion project in Texas.

Centrica seals LNG supply deal with Petrobras

UK-based energy firm Centrica has signed a 15-year LNG supply deal with Brazil’s state-owned energy firm Petrobras.

Japan’s Japex boosts LNG sales

Japan Petroleum Exploration (Japex) boosted its sales of liquefied natural gas (LNG) in the April-December period last year.

More News Like This

Australia’s Omega appoints Martin Houston as chairman

Australia's Omega Oil & Gas has appointed Martin Houston, former chief operating officer of BG and co-founder of Tellurian,...

Hanwha, Baker Hughes to develop ammonia turbines

Two units of South Korean conglomerate Hanwha have joined forces with US energy services firm Baker Hughes to design...

CEO: Baker Hughes expects more than 80 mtpa of LNG FIDs in 2025 and 2026

"For LNG, we still expect 100 mtpa of FIDs (final investment decision) between 2024 and 2026, a level that...

Argent LNG picks Baker Hughes as tech provider

Argent LNG has selected Baker Hughes as the liquefaction solution and related services provider for the planned LNG export...