Novatek says Yamal LNG debt service guarantees removed

Russia‘s Novatek said Thursday the debt service guarantees for its Yamal LNG development were formally removed after the firm completed all the conditions stipulated by the project’s external bank financing.

Novatek’s chief executive and Russian billionaire Leonid Mikhelson said this marks another significant milestone on Yamal LNG.

“The removal of the guarantees will allow Novatek to attract external financing for its new projects on more favorable terms, and equally important, removes the restrictions on our dividend payout ratio,” Mikhelson said.

Yamal LNG is building a 17.4 mtpa LNG export plant comprising of three trains of 5.5 mtpa, each.

Additionally, the project is constructing a smaller LNG train of 900,000 tons per year capacity.

The first LNG train started production in the fourth quarter of 2017. Novatek launched trains 2 and 3 in July 2018 and November 2018, respectively.

Yamal LNG shareholders include Novatek (50.1%), France’s Total (20%), China’s CNPC (20%), and the Silk Road Fund (9.9%).

Most Popular

Australia’s Santos strengthens LNG portfolio with new deals

Australian LNG player Santos has signed two separate, non-binding LNG agreements that underscore the company’s growing global LNG portfolio position. Santos entered into a non-binding heads of agreement to buy LNG from the Ksi Lisims LNG project in Canada and the company agreed key commercial terms with South Korea's Posco Steel to supply the latter with LNG.

Fluxys: Dunkirk LNG sendout reduced due to strike

France’s Dunkirk LNG import terminal has reduced sendout to the grid on Tuesday due to a strike, according to Belgian LNG terminal operator Fluxys.

Sempra Infrastructure, Petrobras ink 20-year Port Arthur LNG SPA

Brazil’s state-owned energy firm Petrobras has signed a long-term deal with US LNG exporter Sempra Infrastructure, a unit of Sempra, to buy LNG from the second phase of the Port Arthur LNG project in Texas.

More News Like This

Arctic LNG 2 seeks $1 billion from Hanwha Ocean over terminated LNG carrier orders

Novatek-led Arctic LNG 2 is seeking approximately $1 billion in damages from South Korean shipbuilder Hanwha Ocean over terminated shipbuilding contracts for Arc7 ice-class LNG tankers.

Zvezda nears delivery of third Russian-built ice-class LNG carrier

Russian Zvezda yard is nearing the delivery of the second Russian-built ice-class liquefied natural gas (LNG) carrier.

Russian LNG production up 12 percent in January-July

Russian liquefied natural gas (LNG) production rose 12 percent in January-July this year, according to the Russian statistics agency Rosstat.

TotalEnergies wraps up transfer of Arctic LNG 2 stake to Novatek

French energy giant TotalEnergies has completed the transfer of a 10 percent stake in the Arctic LNG 2 project to a unit of Russian LNG exporter Novatek.