Dutch Gate terminal resumes ops after maintenance

Dutch Gate LNG import terminal has resumed operations following a planned maintenance turnaround at the facility in the Port of Rotterdam.

Gate, a joint venture of Vopak and Gasunie, had started the maintenance turnaround on June 15. This marked the terminal’s first major maintenance since the launch of operations almost ten years ago.

All services including truck loading, send-out, and jetty operations have resumed on July 11 as planned, after 26 days of maintenance, Gate’s commercial manager Stefaan Adriaens told LNG Prime on Monday.

He added that the maintenance itself was oriented towards overhauling valves.

During the maintenance period, Gate also revealed it had received its first carbon-neutral LNG cargo.

France’s TotalEnergies and Austria’s OMV delivered the LNG shipment from Cheniere’s Sabine Pass terminal on May 5.

In addition, Gate recently said it had taken a final investment decision to increase regasification capacity.

The LNG facility plans to boost its send-out capacity for about 0.5 Bcm per annum to a total of 12.5 Bcm per year.

The additional send-out capacity would become available as of October 1, 2024.

Most Popular

MAN will no longer offer ME-GA engine

Volkswagen’s MAN unveiled the ME-GA dual-fuel engine in March 2021, describing it as an Otto-cycle variant of the company’s...

Kumul awards pre-FEED contract to Wison for Papua New Guinea’s first FLNG

The two firms signed the contract on Friday. With an expected capacity of 1.5 mtpa, Papua New Guinea’s first FLNG...

Atlantic LNG shipping rates dip to $26,750 per day

Last week, Atlantic LNG shipping rates dropped below $50,000 per day. “Spark30S Atlantic rates dropped for a fourth consecutive week,...

More News Like This

Dutch Gate gets first cargo from NFE’s Altamira LNG terminal in Mexico

The 138,000-cbm Energos Princess delivered the maiden cargo from Altamira to the LNG terminal owned by Gasunie and Vopak. Energos...

FID taken on German onshore LNG terminal

"The FID was taken within the last two weeks," a spokesman for German LNG Terminal told LNG Prime on...

Vopak, Transnet moving forward with South African LNG terminal plans

In January, South Africa’s Transnet National Ports Authority appointed the two firms to build and operate the import facility at the...

Gasunie, RWE plan to launch German onshore LNG terminal in 2027

In 2022, Gasunie joined forces with the German government and RWE to build the LNG import terminal, which is worth about...