Finland’s gas system and LNG terminal operator Gasgrid and Estonian gas system operator Elering have shut down the Balticconnector offshore gas pipeline due to a suspected leak.

The 77 kilometers offshore bi-directional pipeline with a capacity of 2.6 bcm stretches from Paldiski, Estonia, to Inkoo, Finland where Gasgrid’s FSRU-based LNG import terminal is located.

Besides the onshore section, the pipeline includes land-based sections in Finland and Estonia.

On October 8, Gasgrid and Elering noticed an “unusual drop in pressure” in the offshore gas pipeline between the two countries shortly before 2 am, according to a statement by Gasgrid.

“Based on observations, it was suspected that the offshore pipeline between Finland and Estonia was leaking. The valves in the offshore pipeline are now closed and the leak is thus stopped,” the firm said.

Gasgrid said it will most likely take at least a few days to inspect the pipeline.

“If it appears that the unusual pressure drop observed in the morning of October 8 in the Balticconnector pipeline is due to a leak caused damage to the pipe, repair work may take at least several months depending on nature of the damage,” it said.

Gasgrid said it is currently investigating the matter in cooperation with Elering.

Elering said in a separate statement that the accident does not affect the gas supply to Estonian consumers.

After the shutdown of Balticconnector, gas reaches Estonian consumers from Latvia, it said.

“Before the closure, Balticconnector operated from Finland to Estonia. Most of the gas that arrived from Finland was forwarded to Latvia,” Elering said.

Inkoo FSRU

Gagrid said that state of the Finnish gas system is “stable”.

The firm said that supply of gas “has been secured through the Inkoo floating LNG terminal for the time being.”

Excelerate Energy’s 150,900-cbm FSRU Exemplar, which serves the Inkoo terminal, has a regasification capacity of more than 5 bcm per year.

In addition to supplying regasified LNG to Finland, the LNG terminal’s biggest customer is Estonia’s Eesti Gaas.

Eesti Gaas received the first LNG cargo via the FSRU Exemplar in April from the US.

It previously said that it plans to receive 11 LNG cargoes via the Inkoo FSRU this year. Eesti Gaas recently received the tenth planned cargo.

Most Popular

MAN will no longer offer ME-GA engine

Volkswagen’s MAN unveiled the ME-GA dual-fuel engine in March 2021, describing it as an Otto-cycle variant of the company’s...

Kumul awards pre-FEED contract to Wison for Papua New Guinea’s first FLNG

The two firms signed the contract on Friday. With an expected capacity of 1.5 mtpa, Papua New Guinea’s first FLNG...

Atlantic LNG shipping rates dip to $26,750 per day

Last week, Atlantic LNG shipping rates dropped below $50,000 per day. “Spark30S Atlantic rates dropped for a fourth consecutive week,...

More News Like This

Eesti Gaas using gas storages in Poland and Germany for winter

LNG importer Eesti Gaas, a unit of Estonian investment firm Infortar, has started using underground gas storage facilities in...

Gasgrid: Inkoo FSRU capacity 50 percent booked in 2025

In July, Gasgrid's unit Floating LNG Terminal Finland offered in total of 22 terminal slots of 950 GWh each...

Finland’s Gasgrid offers Inkoo FSRU capacity for 2025

A unit of Finland’s Gasgrid is offering regasification capacity for 2025 at the FSRU-based LNG import terminal in Inkoo. According...

Gasgrid: Inkoo FSRU capacity 95 percent booked in 2024

Finland’s gas system and LNG terminal operator Gasgrid said companies have booked 95 percent of the offered regasification capacity...