Finland’s Hamina LNG terminal complete, enters commissioning phase

Hamina LNG is nearing the launch of commercial operations at its liquefied natural gas (LNG) import facility in Finland’s Hamina port.

The LNG terminal developer, a joint venture consisting of Finland’s Hamina Energy, tech firm Wartsila, and Estonia’s energy company Alexela, said on Thursday the the facility had achieved mechanical completion and it had started the commissioning phase.

The facility features one tank with a capacity of about 30,000 cbm and will supply about 3 TWh per year to the grid.

It will also offer truck loading services from two bays and bunkering services.

Hamina LNG said in April that it had planned to launch commercial operations at the delayed project in October this year.

After that, it also launched an open season to offer terminal capacity to the market for gas year 2023, starting from October 1, 2022 and ending on September 30, 2023.

According to a statement by Hamina LNG released on Thursday, “the 4800 MWh/d HP injection capacity (transmission network) has been fully booked for the upcoming gas year, but there is still storage capacity and fixed truck loading capacity left.”

The firm is offering the remaining free storage capacity of 12,000 cbm.

Besides this small facility, Finland is also building the FSRU-based terminal in Inkoo as part of plans to boost energy security.

Finnish state-owned natural gas transmission system operator, Gasgrid, is planning to install Excelerate Energy’s FSRU in Inkoo or Estonia’s Paldiski in December this year.

Excelerate’s 150,900-cbm Exemplar will serve Finland, Estonia, and other Baltic states under a 10-year charter deal Gasgrid signed with the US LNG firm in May.

The FSRU, which can supply more than 5 billion cubic meters per year of regasification capacity, is already on its way to Europe from Argentina.

Most Popular

Cheniere produces first LNG cargo at Corpus Christi expansion project

US LNG exporting giant Cheniere has produced the first cargo at the Corpus Christi Stage 3 expansion project in Texas.

Centrica seals LNG supply deal with Petrobras

UK-based energy firm Centrica has signed a 15-year LNG supply deal with Brazil’s state-owned energy firm Petrobras.

Asyad Shipping sells LNG carrier

Oman's Asyad Shipping has sold a 2006-built steam liquefied natural gas (LNG) carrier, according to brokers.

More News Like This

Wartsila to support Balearia’s LNG-powered ferry

Finland’s Wartsila has signed a deal with Spanish ferry operator Balearia to support the latter’s LNG-powered ferry, Margarita Salas. According...

Wartsila to support GasLog’s LNG carrier quintet

A unit of Finland’s Wartsila has signed a deal with Greek shipowner GasLog to support the latter’s five liquefied...

Wartsila wins contract for Gasum’s bio-LNG plant in Sweden

Finland’s tech firm Wartsila said it will supply equipment for Gasum’s new bio-LNG production plant in Sweden. Wartsila booked the...

Wartsila, Capital Gas ink LNG carrier maintenance deal

According to Wartsila, the five-year deal was booked in the third quarter of this year. Warstila did not provide the...