Gasunie aims to wrap up Eemshaven LNG work this week

Dutch gas transmission network operator Gasunie is now hoping to complete maintenance work at its new LNG import hub in the Dutch port of Eemshaven this week.

The new terminal with a capacity of about 8 bcm per year started delivering regasified LNG to the Dutch grid in September in record time.

It features two chartered FSRUs and they include Exmar’s 26,000-cbm barge-based FSRU Eemshaven LNG and the 170,000-cbm Energos Igloo, previously known as Golar Igloo. A joint venture of asset manager Apollo and US LNG firm NFE owns Energos Igloo.

Gasunie’s unit and the terminal operator, EemsEnergyTerminal, started maintenance work at the facility on November 22 and previously expected it to last until November 29.

Last week, a Gasunie spokeswoman told LNG Prime that the company had completed the connection between the two chartered FSRUs and that work was continuing on the heat connection.

The state-owned company hoped to complete this work by December 11. However it took more time than expected.

“This work is now expected to be completed by December 13 – 15,” the spokeswoman told LNG Prime late on Monday.

Full production by January

The Eemshaven LNG hub should welcome the next carrier on December 17, according to the spokeswoman.

Also, the spokeswoman said that Gasunie still expects the terminal to reach full production by January.

Gasunie has been quite busy this year regarding new LNG regasification infrastructure as the Netherlands and other European countries such as Germany look to replace Russian pipeline gas supplies.

The company is now studying to further expand the existing LNG facilities in Eemshaven and in Rotterdam (Gate) on the basis of technical optimizations, it said in a statement on Monday.

Besides the existing facilities, the firm is working on a new FSRU-based facility at the port of Terneuzen.

Most Popular

Venture Global’s Plaquemines LNG to commission fourth tank

US LNG exporter Venture Global LNG has received approval from the US FERC to commission the fourth storage tank with LNG at its Plaquemines plant in Louisiana.

Worley gets full notice to proceed on first phase of CP2 LNG project

Australian engineering firm Worley has received a full notice to proceed from US LNG exporter Venture Global LNG under its reimbursable EPC contract for the first phase of the CP2 LNG project in Louisiana.

US FERC issues final SEIS for NextDecade’s Rio Grande LNG project

The US Federal Energy Regulatory Commission (FERC) has released a final supplemental environmental impact statement for NextDecade's Rio Grande LNG facility and the accompanying pipeline in Texas. FERC continues to conclude that approval of the projects would result in "less than significant impacts."

More News Like This

Netherlands was top destination for US LNG cargoes in May

Dutch Gate and Eemshaven LNG terminals were the top destinations for US liquefied natural gas cargoes in May, according to the Department of Energy’s LNG monthly report.

Dutch Eemshaven LNG terminal boosts volumes in H1

The FSRU-based LNG import facility in the Dutch port of Eemshaven, owned by Gasunie and Vopak, received more LNG in the first half of this year compared to last year, with most of the supplies coming from the US.

Gasunie awards contract for German gas pipeline

A unit of Dutch gas grid and LNG terminal operator Gasunie has awarded a contract for the ETL 182 pipeline, which is expected to meet the anticipated rise in gas transport demand driven by LNG terminals in Brunsbüttel and Stade.

Construction moving forward on German LNG terminal

Dutch gas grid operator Gasunie and German energy firm RWE are moving forward with the construction of the German government-backed onshore LNG import terminal in Brunsbüttel.