Gasunie’s Eemshaven LNG hub to get first cargo as both FSRUs arrive

Gasunie’s new LNG import hub in the Dutch port of Eemshaven will soon receive its first cargo of liquefied natural gas following the arrival of both chartered floating storage and regasification units.

To remind, New Fortress Energy’s 170,000-cbm Golar Igloo entered the Eemshaven port, operated by Groningen Seaports, on Sunday afternoon.

This large unit has now been joined by Exmar’s 26,000-cbm barge-based FSRU Eemshaven LNG.

The small FSRU arrived in Eemshaven under tow on Tuesday.

A spokeswoman for Gasunie told LNG Prime that the 173,000-cbm Murex LNG carrier would deliver the first cargo to EemsEnergyTerminal on Thursday.

The LNG carrier, owned by Seapeak and chartered by Shell, is expected to arrive on Thursday morning in Eemshaven.

According to its AIS data provided by VesselsValue, the LNG carrier previously picked up the cargo at Cheniere’s Sabine Pass LNG plant in Texas.

Gasunie's Eemshaven LNG hub to get first cargo as both FSRUs arrive
Eemshaven LNG (Image: Gasunie)

Dutch LNG imports to jump

Gasunie previously said it would hold an official ceremony to welcome the two FSRUs and the first LNG shipment on September 8, attended by officials from Gasunie, the Czech Prime Minister, and others.

The state-owned firm expects that the new hub would receive up to 18 LNG cargoes by December 31, while regasified LNG from Eemshaven should start flowing through its gas grid in mid-September.

EemsEnergyTerminal, the first FSRU-based facility in the Netherlands, is being prepared in record time as the Netherlands and other European countries such as Germany look to slash reliance on Russian pipeline gas and boost energy security.

LNG giant Shell booked 4 bcm while Czech firm ČEZ took 3 bcm of the terminal’s total capacity. France’s Engie secured the remaining 1 bcm of capacity.

The Eemshaven hub is the second LNG import facility in the Netherlands after the Gate terminal in Rotterdam, which is owned by Gasunie and Vopak.

With an expansion at the Gate terminal and the Eemshaven project, Dutch capacity will double from current 12 bcm to 24 bcm.

Most Popular

Atlantic LNG shipping rates dip below $50,000 per day

Last week, both Atlantic and Pacific LNG shipping rates declined. “Spark30S Atlantic rates dropped for a third consecutive week, reducing...

Inpex restarts second Ichthys LNG train

"I can confirm that Train 2 restarted operations on October 9," the spokesman said. Inpex said on August 22 that the second...

Construction ramping up on Golden Pass LNG project

Golden Pass LNG released a project update via its social media on Monday. "In Sabine Pass, Texas, construction is ramping...

More News Like This

FID taken on German onshore LNG terminal

"The FID was taken within the last two weeks," a spokesman for German LNG Terminal told LNG Prime on...

NFE in $3 billion debt and equity move

On Wednesday, the company issued 46,349,942 shares of its Class A common stock at a public offering price of...

NFE ships first full Altamira LNG cargo to Europe

"NFE’s FLNG asset has achieved first full cargo and sail away, with its first full LNG cargo fully loaded...

Gasunie, RWE plan to launch German onshore LNG terminal in 2027

In 2022, Gasunie joined forces with the German government and RWE to build the LNG import terminal, which is worth about...