Germany’s DET postpones capacity auctions for FSRU terminals

German LNG terminal operator Deutsche Energy Terminal has postponed capacity auctions for its upcoming FSRU-based facilities in Stade in Wilhelmshaven due to delays in project commissioning.

In October last year, DET allocated 60 regasification slots for 2024 at its operational Brunsbüttel and Wilhelmshaven 1 terminals and it also allocated 11 regasification slots at its upcoming FSRU-based LNG import terminal in Stade.

DET planned to hold both short-term and long-term capacity auctions for all four of its FSRU-based terminals in April 2024.

The state-owned firm said in a statement it is currently working “intensely” on the commissioning of the two new LNG terminals Stade and Wilhelmshaven 2.

“However, given the current market status and due to various delays in project commissioning we have decided to defer the anticipated April auctions of 2024 capacity,” it said.

DET said the delay in the auctions is depending on project developments in the coming weeks, and the firm will provide a status update in early April.

Once the performance of the Stade FSRU-based terminal has been tested and confirmed, the remaining slots in addition to the 15 slots already offered in December 2023 will be put up for auction, according to DET.

Also, capacity for the Wilhelmshaven 2 terminal “will only be offered once commissioning dates are more certain,” it said.

DET said the deferral of the auctions will have no influence on sold slots or long-term products.

The delivery for sold slots at Stade (STD01) should not be affected by the commissioning delays, it said.

“In conjunction with the market, DET will also continue to develop products for bookings of 2 to 3 years starting in 2025. These capacities are likely to be offered in summer this year,” DET said.

Stade FSRU arrival

DET told LNG Prime in February that it expects to deploy the Stade FSRU in mid-March.

The 174,000-cbm FSRU Energos Force, previously known as Transgas Force, recently delivered a US LNG cargo to the DET-operated FSRU-based terminal in Brunsbüttel.

After that, the unit visited Rotterdam where minor work was carried out to “convert the ship from cargo operation to FSRU operation,” DET said.

Its AIS data shows that the FSRU left Rotterdam on Wednesday and was on Thursday afternoon nearing Stade.

DET previously said that the FSRU is expected to receive the commissioning cargo in Stade.

Data by Niedersachsen Ports shows that the FSRU is expected to arrive on Friday morning.

As per the second Wilhelmshaven terminal, DET previously said that the company expects commissioning to start at this terminal at the end of the second quarter of 2024.

Excelerate’s FSRU Excelsior is still located at the Navantia yard in El Ferrol, Spain.

Most Popular

Atlantic LNG shipping rates, European prices down

Atlantic LNG freight shipping rates and European prices decreased this week compared to the week before.

Glenfarne becomes majority owner of Alaska LNG

US energy firm Glenfarne has signed definitive agreements with state-owned Alaska Gasline Development Corporation to become the majority owner of the giant Alaska LNG export project.

Petronas to supply LNG to PetroVietnam Gas

Malaysian energy giant Petronas will supply liquefied natural gas (LNG) to PetroVietnam Gas, a unit of state-owned PetroVietnam, next month. The two firms will also look into the possibility of signing long-term LNG contracts.

More News Like This

DET terminates Stade FSRU contract with HEH

State-owned German LNG terminal operator DET has terminated the contract related to the Stade FSRU-based facility with compatriot Hanseatic Energy Hub, the developer of the onshore LNG terminal in Stade.

Egypt, Germany talk FSRU charter terms

Egypt’s Petroleum Minister Karim Badawi has visited Germany's Berlin to talk about contractual terms for the charter of the 174,000-cbm FSRU Energos Power, which previously worked at the Mukran LNG terminal.

Egypt plans to charter FSRU from Germany

Egypt plans to sub-charter the 174,000-cbm FSRU Energos Power, which previously worked at the Mukran LNG terminal, from the German government.

DET expects Excelerate’s FSRU to arrive in Wilhelmshaven in Q1

Excelerate’s 138,000-cbm FSRU Excelsior is expected to arrive in Wilhelmshaven by the end of March, according to state-owned German LNG terminal operator DET.