Germany’s DET postpones capacity auctions for FSRU terminals

German LNG terminal operator Deutsche Energy Terminal has postponed capacity auctions for its upcoming FSRU-based facilities in Stade in Wilhelmshaven due to delays in project commissioning.

In October last year, DET allocated 60 regasification slots for 2024 at its operational Brunsbüttel and Wilhelmshaven 1 terminals and it also allocated 11 regasification slots at its upcoming FSRU-based LNG import terminal in Stade.

DET planned to hold both short-term and long-term capacity auctions for all four of its FSRU-based terminals in April 2024.

The state-owned firm said in a statement it is currently working “intensely” on the commissioning of the two new LNG terminals Stade and Wilhelmshaven 2.

“However, given the current market status and due to various delays in project commissioning we have decided to defer the anticipated April auctions of 2024 capacity,” it said.

DET said the delay in the auctions is depending on project developments in the coming weeks, and the firm will provide a status update in early April.

Once the performance of the Stade FSRU-based terminal has been tested and confirmed, the remaining slots in addition to the 15 slots already offered in December 2023 will be put up for auction, according to DET.

Also, capacity for the Wilhelmshaven 2 terminal “will only be offered once commissioning dates are more certain,” it said.

DET said the deferral of the auctions will have no influence on sold slots or long-term products.

The delivery for sold slots at Stade (STD01) should not be affected by the commissioning delays, it said.

“In conjunction with the market, DET will also continue to develop products for bookings of 2 to 3 years starting in 2025. These capacities are likely to be offered in summer this year,” DET said.

Stade FSRU arrival

DET told LNG Prime in February that it expects to deploy the Stade FSRU in mid-March.

The 174,000-cbm FSRU Energos Force, previously known as Transgas Force, recently delivered a US LNG cargo to the DET-operated FSRU-based terminal in Brunsbüttel.

After that, the unit visited Rotterdam where minor work was carried out to “convert the ship from cargo operation to FSRU operation,” DET said.

Its AIS data shows that the FSRU left Rotterdam on Wednesday and was on Thursday afternoon nearing Stade.

DET previously said that the FSRU is expected to receive the commissioning cargo in Stade.

Data by Niedersachsen Ports shows that the FSRU is expected to arrive on Friday morning.

As per the second Wilhelmshaven terminal, DET previously said that the company expects commissioning to start at this terminal at the end of the second quarter of 2024.

Excelerate’s FSRU Excelsior is still located at the Navantia yard in El Ferrol, Spain.

Most Popular

Another steam LNG carrier sold for demolition

An NYK-managed steam liquefied natural gas (LNG) carrier has been sold for demolition, according to brokers.

Abaxx sees significant volume growth in its LNG futures

Abaxx Commodity Futures Exchange, a wholly owned subsidiary of Abaxx Technologies (CBOE:ABXX) has seen significant volume growth in its physically deliverable LNG futures during the past summer months, according to Abaxx Exchange Chief Commercial Officer Joe Raia.

Shell’s LNG Canada expansion project to get boost from government

Canadian Prime Minister Mark Carney named the planned second phase of Shell's LNG Canada export project as one of the major projects the federal government would help fast-track.

More News Like This

DET: FSRU Hoegh Gannet to get upgrades at Danish yard

The 170,000-cbm FSRU Hoegh Gannet, which serves the Elbehafen LNG import terminal in Germany’s Brunsbüttel, will be relocated to the Danish Fayard shipyard from September 18 until mid-November, according to German LNG terminal operator DET.

Deutsche ReGas: BASF, Equinor book Mukran regas capacity

German chemicals giant BASF and Norwegian energy firm Equinor have booked long-term regasification capacity at the Deutsche ReGas-operated FSRU-based LNG import facility in Mukran, Germany.

Germany’s DET launches commercial ops at second Wilhelmshaven FSRU

Germany's LNG import terminal operator DET will launch commercial operations at its second FSRU-based terminal in Wilhelmshaven on Friday, following the completion of a commissioning phase.

Stade FSRU arrives in Jordan

The 174,000-cbm FSRU Energos Force has arrived in the Jordanian port of Aqaba, according to Egypt's Ministry of Petroleum and Mineral Resources. State-owned German LNG terminal operator DET sub-chartered this 2021-built FSRU for deployment in Jordan, as it works on the next steps for the delayed Stade LNG import facility in Germany.