Work progresses on Gasunie’s Eemshaven LNG import hub

Dutch gas grid and LNG terminal operator, Gasunie, is moving forward with the construction works at its LNG import hub in Eemshaven in order to receive the first shipment in September.

The terminal is being prepared in record time so it can welcome two floating storage and regasification units next month, according to Gasunie.

Gasunie is currently laying the connecting pipeline in the Eemshaven port, operated by Groningen Seaports, it said in an update on Wednesday.

To remind, Belgium’s Exmar and Gasunie signed a five-year charter deal for the 120 meters long FSRU S188 in March.

Following a trip from Singapore, this barge-based FSRU arrived in Rotterdam in June for modification works at the Damen yard.

In the meantime, Exmar also renamed this unit Eeemshaven LNG.

Work progresses on Gasunie’s Eemshaven LNG import hub
Image: Gasunie

Besides this FSRU, Gasunie also signed a charter deal for a larger FSRU with US LNG player New Fortress Energy. The vessel in question is the 170,000-cbm Golar Igloo.

This FSRU was on Wednesday located in Denmark, its AIS data shows.

Gasunie said in a statement earlier this month it expects the two FSRUs to arrive in Eemshaven in early September.

The firms expects first delivery of LNG through the terminal to take place as early as mid-September.

LNG giant Shell booked 4 bcm while Czech firm ČEZ took 3 bcm of the terminal’s total capacity. France’s Engie secured the remaining 1 bcm of capacity.

The Eemshaven hub is the second LNG import facility in the Netherlands after the Gate terminal in Rotterdam, which is owned by Gasunie and Vopak.

With an expansion at the Gate terminal in Rotterdam and the Eemshaven project, Dutch capacity would double from current 12 bcm to 24 bcm.

Most Popular

TotalEnergies CEO expects US financing for Mozambique LNG to be approved in weeks

In May 2020, EXIM voted to amend the agency's previously approved September 2019 direct loan supporting US exports for...

Greek and German firms place orders for LNG-powered vessels in China and Korea

Reports by Intermodal and other brokers suggest that Greece's Sun Enterprises and TMS Group and Germany's Peter Dohle ordered...

PetroVietnam Power: first LNG power plant connected to grid

PV Power said in a statement that the plant generated 50 MW of electricity as part of its testing...

More News Like This

Gasunie, Vopak to decide on Eemshaven LNG extension later this year

The Eeemshaven LNG hub consists of two chartered floating storage and regasification units – the 170,000-cbm FSRU Energos Igloo,...

Gasunie names interim finance chief

Dutch gas grid and LNG terminal operator Gasunie has appointed Jan Boekelman as interim chief financial officer with effect...

Gasunie finance chief to step down next year

At that point, Hermes will have been employed by Gasunie for almost 23 years, more than five of which...

Burckhardt secures German LNG terminal gig

German LNG Terminal, a joint venture which includes Dutch gas grid operator Gasunie and German energy firm RWE selected...