Adani, TotalEnergies welcome first LNG cargo at Dhamra terminal in India

India’s Adani and France’s TotalEnergies have received the first cargo of liquefied natural gas at their Dhamra LNG import facility located in Odisha, on India’s east coast.

The 138,273-cbm Milaha Ras Laffan delivered the commissioning cargo to the Dhamra LNG terminal during the weekend.

According to its AIS data provided by VesselsValue, the 2004-built LNG carrier previously loaded the cargo at the giant Ras Laffan LNG complex, operated by QatarEnergy’s unit Qatargas.

Local media reports suggest that the commissioning of the LNG import facility would take about 45 days, and after that the facility would start commercial operations.

Total Adani, a 50/50 joint venture between Adani and TotalEnergies, owns the Dhamra LNG terminal.

LNG Prime reported in December last year that construction of the LNG import facility was nearing completion.

A unit of TotalEnergies said in February 2021 that the facility was more than 70 percent complete as of December 2020.

Construction of the facility started back in 2018, with India’s Larsen & Toubro responsible for setting up the LNG tanks, while Taiwan’s CTCI Corporation won the contract for the regasification package.

Designed for a capacity of 5 mtpa, the Dhamra terminal features two tanks of 180,000 cbm capacity, each. There is a potential to double the capacity to 10 mtpa.

In addition, the terminal’s jetty is capable of receiving the world’s largest LNG carriers, but also reloading smaller vessels.

TotalEnergies and Adani also plan to distribute LNG via trucks to the region.

As per capacity takers, the JV entered into 20-year LNG regasification agreements with state-owned Indian Oil Corporation (IOC) and GAIL.

This is the seventh operational LNG terminal in India and second on the east coast.

At the moment, India imports LNG via six facilities with a combined capacity of about 42.7 million tonnes.

These include Petronet LNG’s Dahej and Kochi terminals and Shell’s Hazira terminal.

India’s liquefied LNG imports rose for the second month in a row in February due to lower spot prices.

Most Popular

Venture Global launches FID process for CP2 LNG project

US LNG exporter Venture Global LNG said on Thursday that it is launching the final investment decision (FID) process for its proposed CP2 LNG project in Louisiana.

NextDecade plans Rio Grande LNG expansion

US LNG firm NextDecade has revealed plans for up to five more trains at its Rio Grande LNG export plant in Texas.

Venture Global working on Plaquemines LNG expansion

US LNG exporter Venture Global LNG has begun the pre-filing process at the US FERC for a brownfield expansion of its Plaquemines LNG terminal in Louisiana.

More News Like This

Hudong-Zhonghua kicks off work on TotalEnergies LNG bunkering vessel

China’s Hudong-Zhonghua has officially started building one 18,600-cbm LNG bunkering vessel for French energy giant TotalEnergies.

TotalEnergies claims Asia Pacific’s first cruise ship LNG bunkering

A unit of France's TotalEnergies has completed what it says is Asia Pacific’s first LNG bunkering for cruise passenger ships.

Marsa LNG dredging operations start in Oman

Dutch dredging and offshore contractor Boskalis has started dredging operations as part of the TotalEnergies-led Marsa LNG bunkering project...

Eni, TotalEnergies to send Cyprus gas to Egypt’s Damietta LNG export plant

Italy’s Eni and its partner France’s TotalEnergies have agreed with Cyprus and Egypt to send gas from the Cronos gas field off Cyprus to Egypt's Damietta LNG plant, liquefy it, and ship the LNG supplies to Europe.