Cheniere: Corpus Christi LNG expansion project 43 percent complete

US LNG exporting giant Cheniere and compatriot construction and engineering firm Bechtel are moving forward with the construction work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June last year, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the August construction report filed with the US FERC that overall project completion for the Stage 3 project is 42.8 percent.

Stage 3 engineering and procurement are 70.9 percent and 62.3 percent complete, respectively, while subcontract and direct hire construction work are 54 percent and 6.5 percent complete, respectively, it said.

Cheniere: Corpus Christi LNG expansion project 43 percent complete
Cryo piperack — first spools in rack for Train 1 (Image: Cheniere)

First cold boxes arrived

During the month of August, CCL’s contractor continued piling activities, road improvements, drainage work and mobilization of temporary facilities, equipment, and personnel continued during the reporting period, it said.

CCL said that Bechtel has started installation of aboveground piping and it has established a new workstation for double jointing pipe.

In addition, the first cold boxes arrived at the site.

Last year, US equipment manufacturer Chart Industries received full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

CCL said that Bechtel has completed piling work for Trains 1-3 with the same work ongoing for the remaining four trains and OSBL areas.

Steel installation is progressing on schedule in Train 1 and preparations are being made to start steel installation in Train 2.

Additionally, piling installation begun for the 138 kV overhead line transition yard and work on the overhead line poles has started, it said.

Cheniere: Corpus Christi LNG expansion project 43 percent complete
Preparation for piperack foundation pedestals work and feed gas line (Image: Cheniere)

Ahead of schedule

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August that the company is expecting to complete the expansion phase ahead of schedule.

Fusco told analysts during Cheniere’s second-quarter earnings call that Bechtel “continues to progress Corpus Christi Stage 3 well ahead of schedule, increasing my optimism for that project being completed ahead of the guaranteed date.”

“Certain construction activities on Stage 3 are taking place ahead of plan, and I remain optimistic on schedule outperformance and potentially having more LNG volumes in 2025, and possibly the entire seven-train project complete by the end of 2026,” the CEO said.

Most Popular

Aramco eyes large LNG portfolio

Aramco's long-term ambition is to have a portfolio of 20 million tonnes per annum (mtpa) of LNG capacity, according to Aramco’s CEO, Amin Nasser.

Argentina’s Southern Energy takes FID on second FLNG

Argentina's Southern Energy takes FID on second FLNG

YPF CEO sees FIDs on FLNG projects with Eni, Shell in Q1 2026

Argentina’s state-owned oil and gas company YPF and its partners Eni and Shell may take final investment decisions on two stages of the Argentina LNG project in the first quarter of 2026, according to YPF CEO Horacio Marin.

More News Like This

Cheniere, Jera seal long-term LNG SPA

US LNG exporter Cheniere has signed a long-term LNG sale and purchase agreement with Japan's Jera.

Cheniere completes second train at Corpus Christi LNG expansion project

US LNG exporting giant Cheniere has achieved substantial completion of the second liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.

Cheniere to start pre-filing process for Corpus Christi Stage 4 project

US LNG exporting giant Cheniere is seeking approval from the US FERC to initiate the environmental pre-filing review for its Corpus Christi Liquefaction Stage 4 project in Texas.

Port of Corpus Christi: H1 LNG volumes rise 10.8 percent

The US Port of Corpus Christi in Texas reported a 10.8 percent year-on-year increase in its liquefied natural gas (LNG) volumes in the first half of this year.