Cheniere: Corpus Christi LNG expansion project 43 percent complete

US LNG exporting giant Cheniere and compatriot construction and engineering firm Bechtel are moving forward with the construction work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June last year, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the August construction report filed with the US FERC that overall project completion for the Stage 3 project is 42.8 percent.

Stage 3 engineering and procurement are 70.9 percent and 62.3 percent complete, respectively, while subcontract and direct hire construction work are 54 percent and 6.5 percent complete, respectively, it said.

Cheniere: Corpus Christi LNG expansion project 43 percent complete
Cryo piperack — first spools in rack for Train 1 (Image: Cheniere)

First cold boxes arrived

During the month of August, CCL’s contractor continued piling activities, road improvements, drainage work and mobilization of temporary facilities, equipment, and personnel continued during the reporting period, it said.

CCL said that Bechtel has started installation of aboveground piping and it has established a new workstation for double jointing pipe.

In addition, the first cold boxes arrived at the site.

Last year, US equipment manufacturer Chart Industries received full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

CCL said that Bechtel has completed piling work for Trains 1-3 with the same work ongoing for the remaining four trains and OSBL areas.

Steel installation is progressing on schedule in Train 1 and preparations are being made to start steel installation in Train 2.

Additionally, piling installation begun for the 138 kV overhead line transition yard and work on the overhead line poles has started, it said.

Cheniere: Corpus Christi LNG expansion project 43 percent complete
Preparation for piperack foundation pedestals work and feed gas line (Image: Cheniere)

Ahead of schedule

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August that the company is expecting to complete the expansion phase ahead of schedule.

Fusco told analysts during Cheniere’s second-quarter earnings call that Bechtel “continues to progress Corpus Christi Stage 3 well ahead of schedule, increasing my optimism for that project being completed ahead of the guaranteed date.”

“Certain construction activities on Stage 3 are taking place ahead of plan, and I remain optimistic on schedule outperformance and potentially having more LNG volumes in 2025, and possibly the entire seven-train project complete by the end of 2026,” the CEO said.

Most Popular

Venture Global to introduce gas to 9th Plaquemines liquefaction block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the ninth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

Shell’s LNG Canada moving forward with commissioning activities

Shell’s LNG Canada is moving forward with its commissioning and start-up phase and expects to receive a liquefied natural gas (LNG) cargo soon.

Wan Hai Lines to switch methanol containership order to LNG fuel

Taiwan's Wan Hai Lines is working on switching an order placed in South Korea last year for eight methanol-powered containerships to LNG fuel, according to shipbuilding sources.

More News Like This

Corpus Christi LNG expansion project 78.3 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 78.3 percent complete.

Cheniere targets Sabine Pass LNG expansion FID in 2026 or 2027

US LNG exporting giant Cheniere plans to make a final investment decision to expand its giant Sabine Pass LNG plant in Louisiana in late 2026 or 2027, according to its management.

Cheniere still targets 2025 FID on two more Corpus Christi LNG trains

US LNG exporting giant Cheniere still expects to make a final investment decision to build two more midscale trains at its Corpus Christi LNG plant in Texas this year, according to CEO Jack Fusco.

Cheniere produces first LNG cargo at Corpus Christi expansion project

US LNG exporting giant Cheniere has produced the first cargo at the Corpus Christi Stage 3 expansion project in Texas.