Cheniere seeks more time for Corpus Christi LNG expansion

US LNG exporting giant Cheniere asked US energy regulators for an extension to construct the proposed Stage 3 expansion at its Corpus Christi export plant in Texas.

The Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

Under the expansion project, Cheniere plans to build up to seven mid-scale liquefaction trains with a total expected nominal production capacity of about 10 mtpa.

The US FERC approved this expansion project back in November 2019. Under this approval, Cheniere and its units have to complete the project in five years or until around November 2024.

Cheniere’s units asked FERC in a filing dated December 7 to extend this date until June 2027.

“The onset and duration of the Covid-19 pandemic resulted in adverse economic and logistical conditions that slowed commercial progress and precluded CCL Stage III from making a timely final investment decision (FID) on the Stage 3 project in order to meet the current permitted construction duration,” Cheniere said in the filing.

This delay in full commercialization has resulted in the need for additional time to construct and place the Stage 3 project in service, Cheniere said.

Close to FID

While the Covid-19 pandemic caused significant impact to global markets last year, global LNG demand and long-term contracting activity have experienced significant growth in 2021, according to Cheniere.

“During the last 12 months alone, Cheniere Energy and its affiliates have signed about 6 mtpa of long-term contracts, which, alongside long-term contracts previously signed, means that commercialization for the Stage 3 project is close to completion,” it said.

The strong global LNG market continues to drive commercial momentum, and CCL Stage III
anticipates “imminently restarting” early construction activities at the Stage 3 project site and making a positive FID during 2022, Cheniere said.

Full construction of the expansion facilities would commence upon making a positive FID.

Based on a June 2022 FID and a 60-month construction duration, the Stage 3 project would be made available for service by June 2027, Cheniere said.

Most Popular

Energy Transfer’s Lake Charles LNG secures DOE extension

Texas-based Energy Transfer has secured a permit extension from the US DOE to start exports from its proposed Lake Charles LNG export facility in Louisiana.

Shell adds another LNG carrier to its fleet

A unit of UK-based LNG giant Shell has added another chartered liquefied natural gas carrier to its fleet.

Nigeria LNG seals long-term gas supply deals

LNG producer Nigeria LNG, a joint venture of NNPC, Shell, TotalEnergies, and Eni, has signed six long-term gas agreements to secure supplies for its Bonny Island plant, including the terminal's expansion.

More News Like This

Cheniere nears first LNG at third Corpus Christi expansion train

US LNG exporter Cheniere is nearing the start of LNG production at the third train of the Corpus Christi Stage 3 expansion project in Texas as part of the commissioning phase.

Cheniere, Jera seal long-term LNG SPA

US LNG exporter Cheniere has signed a long-term LNG sale and purchase agreement with Japan's Jera.

Cheniere completes second train at Corpus Christi LNG expansion project

US LNG exporting giant Cheniere has achieved substantial completion of the second liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.

Cheniere to start pre-filing process for Corpus Christi Stage 4 project

US LNG exporting giant Cheniere is seeking approval from the US FERC to initiate the environmental pre-filing review for its Corpus Christi Liquefaction Stage 4 project in Texas.