Cheniere wins approval to introduce feed gas to sixth Sabine Pass train

US LNG exporter Cheniere has won approval to introduce feed gas to the sixth production train at its Sabine Pass liquefaction plant in Louisiana.

LNG Prime reported last week that the firm’s unit was seeking approval from the Federal Energy Regulatory Commission (FERC).

FERC said in a filing dated September 22 it had granted Sabine Pass to introduce feed gas to commission “certain portions of Train 6.”

The energy regulator added that this approval does not grant Sabine Pass the authority to
commission other project facilities at the LNG facility.

Cheniere’s chief executive Jack Fusco said in August the firm had started early commissioning activities at the sixth Sabine Pass production train.

Fusco also said that the project had reached 89.6 percent completion as of the end of June.

In addition, Cheniere expects substantial completion at the liquefaction unit in the first quarter of 2022.

The 25 mtpa Sabine Pass plant has five operational trains and is currently the largest such facility in the US.

Bechtel is building the sixth train which will add 5 mtpa of capacity to the facility.

In total, this is the ninth train the engineering giant is building for Cheniere, including the Corpus Christi plant where Bechtel handed over the third train earlier this year.

Most Popular

TotalEnergies board backs CEO Pouyanne for another term

French energy giant and LNG player TotalEnergies said ​on Friday that ‌its board unanimously ​backed ​the renewal of ⁠chairman ​and ​CEO Patrick Pouyanne's mandate.

NYK’s LNG carrier named in South Korea

South Korea’s Hyundai Samho hosted a naming ceremony for a new liquefied natural gas (LNG) carrier owned by Japan's NYK and chartered by Mitsubishi’s unit Diamond Global Energy.

Atlantic LNG rates rise to almost $30,000 per day

Atlantic spot LNG shipping rates rose for the fourth week in a row, reaching almost $30,000 per day, according to Spark Commodities.

More News Like This

FERC issues draft EIS for Cheniere’s Corpus Christi Stage 4 project

The US Federal Energy Regulatory Commission (FERC) has released a draft environmental impact statement for Cheniere’s planned Corpus Christi Liquefaction Stage IV expansion project in Texas. The regulator concluded that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”

Glenfarne’s Magnolia LNG secures FERC extension

Glenfarne’s Magnolia LNG has secured a five-year extension from the US FERC to complete construction and place into service its planned liquefaction and export plant in Louisiana.

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Equinor takes first LNG cargo from Cheniere

Norwegian energy firm Equinor has taken delivery of its first liquefied natural gas (LNG) cargo under long-term supply agreements with US LNG exporting giant Cheniere.