Cheniere’s Corpus Christi LNG expansion project 62.4 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 62.4 percent complete, and the US LNG exporting giant is working to start production at the first train later this year.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and compatriot Bechtel officially started construction on the project in October the same year.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the June construction report filed with the US FERC on Monday that overall project completion for the Stage 3 project is 62.4 percent.

The project was 57.6 percent complete as of April 31, 2024.

Stage 3 engineering and procurement are 93.7 percent and 80.3 percent complete, respectively, while subcontract and direct hire construction work are 83.9 percent and 24.4 percent complete, respectively.

Energization of first train

During the month of June, CCL’s contractor achieved energization of the train 1 liquefaction and utility substations, it said.

Moreover, Bechtel continued road improvements, drainage work and mobilization of temporary facilities, equipment, and personnel during the reporting period.

Concrete work continues in trains 2 – 6, and outside boundary limits (OSBL), while structural steel started in train 4 and continues in trains 2, 3, and OSBL.

Underground piping is progressing in trains 1 – 6 and OSBL, and equipment setting is ongoing in trains 1 – 4, CCL said.

During July, Bechtel will continue installation of pipe spools in the cryogenic and AGRU pipe racks at the first train and continue testing of aboveground piping.

Cheniere’s Corpus Christi LNG expansion project 62.4 percent complete
Corpus Christi Stage 3 in March 2024 (Image: Cheniere)

First LNG production in 2024

Cheniere initially said that LNG deliveries from the expansion project were expected to begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

The company confirmed in its first quarter report that it expects to achieve first LNG production from the first train at the end of 2024.

Substantial completion of the project is expected during 1H 2025 – 2H 2026.

Besides this expansion, Cheniere plans to build two more liquefaction trains as part of the third expansion phase at the Corpus Christi plant.

Cheniere aims to to take a final investment decision on this project in 2025.

In addition, Cheniere also aims to build two new liquefaction trains as part of the Sabine Pass Stage 5 expansion project to add up to 20 mtpa of capacity to the giant 30 mtpa facility.

Most Popular

Excelerate buys GasLog LNG carrier

US FSRU player Excelerate Energy has purchased a 2007-built steam liquefied natural gas (LNG) carrier from GasLog Partners, a part of Greek LNG shipping firm GasLog, according to brokers.

NextDecade, Bechtel agree $9 billion EPC deals for two Rio Grande LNG trains

US LNG firm NextDecade and compatriot Bechtel have finalized EPC contracts worth $9.09 billion for the construction of the fourth and fifth trains and related infrastructure at the Rio Grande LNG facility in Texas.

Venture Global gets FERC OK to boost Calcasieu Pass LNG capacity

US LNG exporter Venture Global LNG has received approval from the US FERC to increase the peak liquefaction capacity of its Calcasieu Pass LNG terminal in Louisiana.

More News Like This

Japan’s Jera seals US LNG supply deals

Japan's power firm and LNG trader Jera has signed 20-year agreements to buy up to 5.5 million tonnes per year of LNG from the United States. The deals include an SPA with Commonwealth LNG and the previously announced SPA with NextDecade, as well as heads of agreements with Sempra Infrastructure and Cheniere.

Cheniere aims to start construction on Sabine Pass LNG expansion in late 2026

US LNG exporting giant Cheniere aims to start construction on the proposed expansion project at its Sabine Pass LNG export facility in Louisiana in late 2026.

Cheniere’s Corpus Christi expansion project almost 84 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 84 percent complete.

Port of Corpus Christi completes ship channel expansion

The US Port of Corpus Christi in Texas has completed the $625 million ship channel improvement project.