Cheniere’s Corpus Christi LNG expansion project almost 50 percent complete

US LNG exporting giant Cheniere and compatriot Bechtel are moving forward with the construction work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June last year, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the November construction report filed with the US FERC that overall project completion for the Stage 3 project is 48.8 percent.

Stage 3 engineering and procurement are 80 percent and 69 percent complete, respectively, while subcontract and direct hire construction work are 63.1 percent and 9.8 percent complete, respectively, it said.

Cheniere's Corpus Christi LNG expansion project almost 50 percent complete
Train 1 air-cooled heat exchangers (Image: Cheniere)

Work progressing

During November, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

Piling and soil stabilization teams are making progress in Trains 5 and 6, as well as OSBL phase, the firm said.

Concrete work is progressing in train 2 and OSBL south. Aboveground piping continues to be connected and integrated with pipe spools in the train 1 cryo racks and will continue in the AGRU area in the upcoming weeks, it said.

Key equipment installations include the train 1 cold boxes, utility substation, and hot oil furnace.

In August, first cold boxes arrived at the site.

Last year, US equipment manufacturer Chart Industries received full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

Cheniere’s unit said that additional major installations are planned for December 2023, such as the GIS substation and the first refrigeration compressor.

Ahead of schedule

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

Cheniere's Corpus Christi LNG expansion project almost 50 percent complete
East ground flare 1 (Image: Cheniere)

However, Cheniere’s CEO Jack Fusco said in August that the company is expecting to complete the expansion phase ahead of schedule.

He said in November that construction on Corpus Christi Stage 3 “continues to progress ahead of plan, and I am optimistic first LNG production from train 1 will occur by the end of 2024.”

The expansion project was 44.1 percent complete as of September 30.

Most Popular

Aramco eyes large LNG portfolio

Aramco's long-term ambition is to have a portfolio of 20 million tonnes per annum (mtpa) of LNG capacity, according to Aramco’s CEO, Amin Nasser.

Argentina’s Southern Energy takes FID on second FLNG

Argentina's Southern Energy takes FID on second FLNG

YPF CEO sees FIDs on FLNG projects with Eni, Shell in Q1 2026

Argentina’s state-owned oil and gas company YPF and its partners Eni and Shell may take final investment decisions on two stages of the Argentina LNG project in the first quarter of 2026, according to YPF CEO Horacio Marin.

More News Like This

Cheniere, Jera seal long-term LNG SPA

US LNG exporter Cheniere has signed a long-term LNG sale and purchase agreement with Japan's Jera.

Cheniere completes second train at Corpus Christi LNG expansion project

US LNG exporting giant Cheniere has achieved substantial completion of the second liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.

Cheniere to start pre-filing process for Corpus Christi Stage 4 project

US LNG exporting giant Cheniere is seeking approval from the US FERC to initiate the environmental pre-filing review for its Corpus Christi Liquefaction Stage 4 project in Texas.

Port of Corpus Christi: H1 LNG volumes rise 10.8 percent

The US Port of Corpus Christi in Texas reported a 10.8 percent year-on-year increase in its liquefied natural gas (LNG) volumes in the first half of this year.