Chevron working to resume full Gorgon LNG production after electrical incident

Chevron’s unit in Australia is working to return to full production from its Gorgon LNG plant in Western Australia following an electrical incident affecting one of the plant’s three trains.

The Gorgon LNG plant on Barrow Island has three trains and a production capacity of some 15.6 mtpa.

“The incident occurred about 1.30am AWST on Tuesday, October 31, in a substation which provides power supply,” a Chevron Australia spokesperson told LNG Prime on Thursday.

“Personnel were not in the substation at the time of the incident, and no one was harmed,” the spokesperson said.

According to Chevron’s spokesperson, the production train is currently producing at “about 80 percent capacity.”

“Domestic gas and the remaining two LNG production trains at Gorgon are unaffected and are producing at full rates,” the spokesperson said.

Chevron and its workers at the Gorgon and Wheatstone LNG terminals recently agreed on new labor agreements following lengthy negotiations between Chevron and unions representing the workers.

In September, Chevron also resumed full production at its 8.9 mtpa Wheatstone LNG terminal near Onslow after a fault reduced about 25 percent of the plant’s production.

Most Popular

Woodside terminates Commonwealth LNG SPA

Australian LNG player Woodside has terminated its two LNG sale and purchase agreements with US LNG terminal developer Commonwealth LNG.

Energy Transfer seals Lake Charles LNG supply deals

Texas-based Energy Transfer has signed new supply deals for its planned Lake Charles LNG export facility in Louisiana as it works to take a final investment decision by the end of this year, according to its management.

Thailand in Alaska LNG talks

Thailand's PTT and Egco will engage in further discussions to potentially participate in the development and buy volumes from the planned Alaska LNG project, according to Thailand's Ministry of Energy.

More News Like This

Chevron: production at first Wheatstone LNG train reduced due to maintenance

Production at the first liquefaction train of Chevron's Wheatstone LNG plant near Onslow has been reduced due to maintenance, a Chevron Australia spokesperson told LNG Prime on Tuesday.

Tokyo Gas to buy US shale gas stake from Chevron

Japan’s city gas supplier and LNG importer, Tokyo Gas, has agreed to buy a stake in a US shale gas development from energy giant Chevron.

Energy Transfer, Chevron ink long-term Lake Charles LNG deal

Energy Transfer LNG, has entered into a 20-year LNG sale and purchase agreement (SPA) with Chevron U.S.A., according to...

Chevron and Woodside in Australian LNG asset swap deal

The two firms announced the deal in separate statements on Thursday. Under the proposed transaction, Chevron Australia will transfer to...