Chevron working to resume full Gorgon LNG production after electrical incident

Chevron’s unit in Australia is working to return to full production from its Gorgon LNG plant in Western Australia following an electrical incident affecting one of the plant’s three trains.

The Gorgon LNG plant on Barrow Island has three trains and a production capacity of some 15.6 mtpa.

“The incident occurred about 1.30am AWST on Tuesday, October 31, in a substation which provides power supply,” a Chevron Australia spokesperson told LNG Prime on Thursday.

“Personnel were not in the substation at the time of the incident, and no one was harmed,” the spokesperson said.

According to Chevron’s spokesperson, the production train is currently producing at “about 80 percent capacity.”

“Domestic gas and the remaining two LNG production trains at Gorgon are unaffected and are producing at full rates,” the spokesperson said.

Chevron and its workers at the Gorgon and Wheatstone LNG terminals recently agreed on new labor agreements following lengthy negotiations between Chevron and unions representing the workers.

In September, Chevron also resumed full production at its 8.9 mtpa Wheatstone LNG terminal near Onslow after a fault reduced about 25 percent of the plant’s production.

Most Popular

Atlantic LNG shipping rates down, Pacific rates climb

Atlantic spot LNG shipping rates dropped this week, while Pacific rates rose compared to the week before, according to Spark Commodities.

Cheniere nears launch of seventh Corpus Christi expansion train

US LNG exporter Cheniere is close to launching the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Vietnam’s Cai Mep LNG terminal starts gas deliveries to Phu My power complex

Nebula Energy’s AG&P LNG has started delivering natural gas from Vietnam's Cai Mep liquefied natural gas (LNG) import terminal to the 900 MW Phu My 2.1 and 2.1E power plants operated by EVNGENCO3.
spot_img

More News Like This

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.

MOL’s newbuild LNG carrier gets sails in South Korea

South Korea's Hanwha Ocean has completed the world’s first installation of the wind challenger system on an LNG carrier. The LNG carrier is owned by Japan's MOL and chartered by US energy giant Chevron.

Chevron resumes full Wheatstone LNG production after repairs

Chevron has resumed full production at the Wheatstone LNG facility near Onslow in Western Australia following the completion of repairs after Tropical Cyclone Narelle.

Chevron says Wheatstone LNG plant operating at 50 percent capacity

Chevron's Wheatstone LNG facility near Onslow in Western Australia is now operating at 50 percent capacity, while repairs continue on the second liquefaction train, a Chevron Australia spokesperson told LNG Prime on Thursday.