Chevron wraps up Gorgon LNG repairs

US energy giant Chevron has completed repairing heat exchangers at the third Gorgon LNG train in Western Australia.

Chevon said in May it had started working on the third train at its giant 15.6 mtpa LNG facility on Barrow Island after finding “weld quality issues” that closed the plant’s first and second train.

“Repairs to the Gorgon propane heat exchangers are complete,” Jay Johnson, Chevron’s upstream chief told analysts during the company’s second-quarter earnings call on Friday.

He added that all Gorgon trains now produce LNG in Australia.

The Gorgon development is one of the world’s largest natural gas projects with a price tag of about $54 billion.

The plant liquefies gas coming from two offshore fields – Gorgon and Jansz-Io.

The first LNG cargo departed Barrow Island in March 2016 followed by gas supply to the domestic market in December.

Chevron Australia operates the project with a 47.3% share while ExxonMobil and Shell have a 25% stake, each.

Japan’s Osaka Gas, Tokyo Gas, and JERA own the remaining stakes in Gorgon.

Most Popular

Eni seeks contractors for third Mozambique FLNG

Italian energy firm Eni and its partners in the Mozambique Rovuma Venture have invited companies to submit their expression of interest for the construction of one large floating LNG production unit with a capacity of up to 6 mtpa.

Vitol, IRH finalize 20-year LNG supply deal

Energy trader Vitol and UAE-based International Resources Holding (IRH) have signed a 20-year LNG sales and purchase agreement for volumes from Delfin Midstream’s floating LNG project in the US.

Golden Pass LNG gets green light to start commissioning of second train

Golden Pass LNG, a joint venture of energy giants QatarEnergy and ExxonMobil, has secured approval from the US FERC to kick off the commissioning process for the second liquefaction train at its three-train plant in Texas.

More News Like This

MOL’s newbuild LNG carrier gets sails in South Korea

South Korea's Hanwha Ocean has completed the world’s first installation of the wind challenger system on an LNG carrier. The LNG carrier is owned by Japan's MOL and chartered by US energy giant Chevron.

Chevron resumes full Wheatstone LNG production after repairs

Chevron has resumed full production at the Wheatstone LNG facility near Onslow in Western Australia following the completion of repairs after Tropical Cyclone Narelle.

Chevron says Wheatstone LNG plant operating at 50 percent capacity

Chevron's Wheatstone LNG facility near Onslow in Western Australia is now operating at 50 percent capacity, while repairs continue on the second liquefaction train, a Chevron Australia spokesperson told LNG Prime on Thursday.

Chevron says all Gorgon LNG trains operating, Wheatstone damaged

All three liquefaction trains at Chevron's giant Gorgon LNG plant on Barrow Island are now operational following a powerful tropical cyclone in Western Australia, a Chevron Australia spokesperson told LNG Prime on Sunday.