Coastal GasLink to begin laying LNG Canada pipeline

TC Energy-led Coastal GasLink is to start laying a giant pipeline that will supply natural gas to the Shell-led LNG Canada project in July.

Coastal GasLink is building a 667-kilometer-long pipeline worth about C$6.6 billion.

The pipeline will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat, British Columbia.

Coastal GasLink said it has selected Toronto-based Aecon Group as prime contractor for construction of the compressor and metering stations. These facilities will become the anchor points of the giant pipeline.

The initial phase of the project includes the Wilde Lake compressor station and the Kitimat meter station.

Construction of the Wilde Lake facility will kick off in July 2020, as part of the company’s summer construction program,

Work across the route will gradually ramp up over the coming months, in advance of peak activity in September.

“Work over the coming weeks will focus on environmental monitoring and field work, grading, grubbing and workforce accommodation”, the company said.

This is to position the project for pipe assembly and installation later this summer.

Pipe deliveries will also continue with pipe stringing and assembly starting early July in multiple areas across the project.

According to Coastal GasLink, the project’s first in-field pipeline weld took place in Kitimat earlier this month.

The pipeline operator added that with this work comes additional workforce requirements, ultimately growing to over 2,500 by September.

Coastal GasLink announced a positive final investment decision to build the pipeline following a go-ahead from its partner, LNG Canada, on October 2, 2018.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation and Kogas of South Korea.

The joint venture of JGC-Fluor Corporation is the project’s engineering, procurement and construction contractor.

LNG Canada will initially build two trains with a capacity to produce 14 million tonnes of LNG per year.

The project, worth more than $30 billion, is one of the largest megaprojects in Canadian history.

Most Popular

Celsius takes delivery of new LNG tanker

South Korea’s Samsung Heavy Industries has handed over a new 180,000-cbm LNG carrier to Denmark’s Celsius Tankers, a unit...

CEO: TotalEnergies looking to restart Mozambique LNG by end of 2024

Pouyanne discussed the Mozambique LNG project during TotalEnergies’ strategy and outlook presentation in New York on Wednesday. According to the...

Hanwha Ocean to build FSRU for $413 million

Hanwha Ocean revealed the order on Wednesday, saying it would build the unit for an unidentified Asian owner. The delivery...

More News Like This

Peru LNG terminal sent six cargoes in September

According to the shipment data by state-owned Perupetro, during August, the 4.4 mtpa LNG plant sent three shipments to...

Shell Marine gets new head

The appointment is effective from October 1, 2024, according to Shell Marine. Dabboussi will replace Melissa Williams who will transition...

Shell’s LNG Canada terminal more than 95 percent complete

Klein said in the newest project update on Thursday that 35,000-plus individual Canadians have worked on the LNG Canada...

Peru LNG terminal sent four cargoes in August

According to the shipment data by state-owned Perupetro, during August the 4.4 mtpa LNG plant sent two shipments to...