Construction progresses on new Grain LNG tank

National Grid and its contractors are moving forward with the construction of a 190,000 cbm LNG tank at the UK’s Isle of Grain facility as part of an expansion project that will boost the terminal’s capacity.

Back in 2021, National Grid awarded the EPC deal to three units of French construction firm Vinci.

This full containment facility worth about 200 million euros ($217 million) will have a 9 percent nickel steel inner tank with a pre-stressed concrete outer shell, poured in-situ using slipforming, according to Vinci.

Naitional Grid said in a construction update issued via its social media on Thursday that the “outer concreting of the huge roof has just been completed, with work continuing on the specialist inner tank.”

“At 190,000 cbm, the new tank is large enough to contain London’s Royal Albert Hall – and store enough energy for everyone in the world to make three cups of tea,” the company claims.

Construction progresses on new Grain LNG tank
Image: National Grid

National Grid added that it expects to complete construction in summer 2025, increasing Grain LNG’s capacity to 1.2 bcm (equal to 33 percent of UK gas demand), and supporting security of supply across Britain and Europe.

State-owned LNG giant QatarEnergy booked capacity from 2025 as part of the expansion of the Grain terminal.

Currently, Europe’s largest LNG terminal has 1 bcm of LNG storage capacity spread across eight tanks and an annual throughput capacity of 20 bcm.

Capacity auction

In September, Grain LNG launched an auction for 375 GWh/d (about 9 mtpa) of existing capacity.

Gtrain LNG is is offering three lots and each lot consists of 42 berthing slots, 200,000 cbm of storage and 125GWh/d (about 3 mtpa) of regasification capacity from as early as January 2029.

This process will run until November 23.

Construction progresses on new Grain LNG tank
Image: National Grid

The LNG terminal welcomed 102 ships during the financial year which ended in March, breaking its previous record of 71 ships set in the financial year 2019 – 2020.

Also, the LNG terminal has sent 102,589 GWh of gas into the grid over the twelve-month period ending May 31, the equivalent of almost 14 percent of total UK gas demand.

National Grid owns the terminal, infrastructure and storage tanks, and works with a range of customers who use the terminal.

The primary customers include BP/Sonatrach, Centrica, Pavilion Energy, TotalEnergies, and Uniper, according to National Grid’s website.

Most Popular

Update: Venture Global ships first Plaquemines LNG cargo to Germany

Venture Global’s 174,000-cbm newbuild carrier, Venture Bayou, is expected to deliver the shipment to Germany’s Brunsbüttel around January 8,...

CIMC SOE clinches LNG bunkering vessel order from Singapore’s EMF

CIMC SOE said on Thursday the vessel will have a capacity of 20,000 cbm. According to CIMC SOE, the dual-purpose...

South Korea’s SK Gas launches LNG, LPG power plant in Ulsan

Commercial operations of Ulsan GPS started on December 26, according to a statement by SK Gas, a unit of...

More News Like This

UK’s Grain LNG gets MiQ methane emissions certification

National Grid's Grain LNG facility in the UK, Europe’s largest LNG import terminal, has received certification from MiQ for...

National Grid to sell Grain LNG terminal

British power and gas utility National Grid said it aims to sell its Grain liquefied natural gas facility, Europe's...

Repsol, Centrica seal LNG supply deal

UK-based energy firm Centrica has signed a deal with Spain's Repsol to buy liquefied natural gas (LNG) from the...

Venture Global books capacity at UK’s Grain LNG terminal

US LNG exporter Venture Global LNG has booked long-term capacity at National Grid’s Grain LNG import terminal in the...