Construction progresses on Sempra’s Port Arthur LNG export project

US LNG exporter Sempra and compatriot Bechtel are moving forward with construction on the first phase of the Port Arthur LNG export project in Texas worth about $13 billion.

In March last year, Sempra Infrastructure, a unit of Sempra, took a final investment decision for the first phase of its Port Arthur LNG export project.

The first phase of the project is fully subscribed with 10.5 mtpa under binding long-term agreements.

Sempra Infrastructure entered into long-term agreements with each of ConocoPhillips, Ineos, Engie, RWE, and PKN Orlen.

Besides a 20-year LNG SPA for 5 mtpa of LNG, US energy giant ConocoPhillips is a shareholder in the project with a 30 percent stake.

Last year, Sempra Infrastructure also completed the sale of a 42 percent non-controlling interest in its Port Arthur LNG Phase 1 project to compatriot private equity firm KKR.

Sempra Infrastructure has a controlling 28 percent indirect interest in Phase 1 at the project level.

Pile driving

Bechtel won the EPC contract which includes building two trains with a total capacity of about 13 mtpa and two storage tanks with a capacity of 160,000 cbm.

Also, Bechtel awarded Port Arthur LNG contracts to Air ProductsElliott, and Great Lakes Dredge & Dock.

The expected commercial operation dates for train 1 and train 2 are 2027 and 2028, respectively.

Sempra Infrastructure’s unit Port Arthur LNG said in a monthly status report filed with FERC that construction-related activities during June 2024 included soil stabilization activities, installation of concrete and sheet piling, foundation work erection of main pipe rack, steel structures, and the continued inspection and maintenance of ECD’s.

According to Port Arthur LNG, Bechtel continued driving piles in OSBL areas, MOF construction activities, perimeter sheet piling for marine berth, and started installation of Dolphin piles.

The firm said that Bechtel continued MOF construction activities, sheet piling for marine berth and berm.

Bechtel continued foundation, grounding work, and structural steel erection in ISBL train 1, started UG pipe installation in ISBL train 1, and continued double-joint pipe welding in laydown areas.

In addition, Bechtel continued driving piles in ISBL train 2, started tank A and tower crane foundation work, and continued construction of laydown areas.

During July, Bechtel will continue site preparation, soil stabilization, wick drain and structural fill placement, as well as continue with driving piles in train 2, tank B, ground flare, refrigerant, and utilities.

Bechtel will continue sheet piling for the marine berth, continue foundation, grounding work, and
structural steel erection in ISBL train 1, and complete round lake crossing.

Port Arthur LNG also said that dredging activities will start in July.

Construction progresses on Sempra’s Port Arthur LNG export project
Image: Port Arthur LNG

Expansion

Besides the first phase, Sempra Infrastructure is also working on the second Porth Arthur LNG phase.

In September last year, Sempra Infrastructure won approval for the US FERC for the proposed Phase 2 project, that includes the addition of two liquefaction trains capable of producing up to 13 mtpa of LNG.

The development of the proposed project would increase the total liquefaction capacity of the facility from some 13 mtpa to about 26 mtpa.

The proposed project would also include an additional LNG storage tank and marine berth and would benefit from some of the common facilities currently under construction that were previously approved as part of the Phase 1 permitting process.

Justin Bird, CEO of Sempra infrastructure, said during Sempra’s second-quarter earnings call in August last year that the company has made “significant progress” on its LNG strategy and “are very bullish on both Port Arthur Phase 2 and Cameron Phase 2 moving forward next year.”

However, the Biden administration said in January it will pause pending decisions on exports of LNG to non-FTA countries until the Department of Energy can update the underlying analyses for authorizations.

DOE still needs to approve Sempra Infrastructure’s non-FTA application for the second phase of the Port Arthur LNG project.

Bird said in February during Sempra’s fourth quarter earnings call that Sempra is now awaiting the DOE non-FTA export permit.

“We’re continuing to work with Bechtel on an EPC agreement that can optimize efficiencies with the Phase 1 construction schedule,” he said.

“And we’re continuing our marketing efforts for offtake and equity and having financing discussions with potential lenders,” Bird said.

Aramco deal

Saudi Arabia’s energy behemoth Aramco recently also signed a non-binding deal with Sempra to buy LNG from the second phase of the Port Arthur LNG export project.

Under the heads of agreement, Aramco aims to buy 5 mtpa of LNG for 20 years from the Port Arthur LNG expansion project.

The HoA further contemplates Aramco’s 25 project participation in the project-level equity of the second phase, the two firms said.

Sempra and Aramco expect to execute a binding LNG SPA and definitive equity agreements with terms substantially equivalent to those in the HoA, with the SPA and equity agreements subject to a number of conditions, they said.

Sempra says that Port Arthur LNG has potential to expand to a total of eight trains, which would position it as one of the world’s “most significant LNG export facilities”.

Most Popular

Venture Global’s vessel arrives at Plaquemines LNG plant

The 174,000-cbm LNG carrier was on Tuesday located at the LNG plant along the Mississippi River, according to its...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

Japan’s K Line on track with LNG fleet growth plans

According to K Line's latest financial report, the firm had 46 LNG carriers in its fleet as of the...

More News Like This

Sempra expects non-FTA approval for Port Arthur LNG expansion in H1 2025

Sempra Infrastructure previously won approval from the US FERC for the proposed Phase 2 project, and it also secured the FTA...

Bechtel secures NTLNG gig from Tamboran

NYSE and ASX-listed Tamboran awarded Bechtel the contract for the LNG terminal at Middle Arm in Darwin in August. According...

US yards to build Port Arthur LNG tugs

Two RApport 2800 tugs will be constructed by Master Boat Builders in Coden, Alabama, and two by Sterling Shipyard...

Cheniere’s Sabine Pass LNG terminal prepares for Tropical Storm Francine

According to the US National Hurricane Center, Tropical Storm Francine is expected to strengthen into a Category 1 hurricane...