Delfin expects to take FID on first floating LNG producer in October

Delfin Midstream, the US developer of a floating LNG export project in the Gulf of Mexico, expects to take a final investment decision on its first floating LNG producer in October this year.

Earlier this year, Delfin said in its March corporate presentation that it expected that technical, commercial, and financing workstreams for the first FLNG were “on track” for an FID in the second quarter.

Delfin plans to install up to four self-propelled FLNG vessels that could produce up to 13.3 mtpa of LNG or 1.7 billion cubic feet per day of natural gas as part of its Delfin LNG project.

The firm also aims to install two FLNG units under the Avocet LNG project.

$18 billion

Delfin has been quite busy this year and it recently sealed a supply deal with UK-based Cetnrica worth about $8 billion.

Prior to that, the firm secured an investment from Japan’s shipping giant MOL and previously signed supply deals with Hartree Partners and Vitol.

In addition to these agreements, Delfin LNG entered into a heads of agreement in September last year with US oil and gas producer Devon Energy for long-term liquefaction capacity, but also a pre-financial investment decision strategic investment.

According to a filling with FERC dated July 21, Delfin’s unit Delfin LNG expects to execute “very soon” a binding LNG offtake agreement with Devon as part of the larger agreement announced in September.

The deal is for 1 mtpa of LNG.

Taken together, all these four LNG offtake agreements will provide revenue to Delfin LNG of about $18 billion over their contract terms, the firm told FERC.

Extension

Last year, the US FERC granted a one-year extension of time, to September 28, 2023, to Delfin to construct and make available for service the LNG project’s onshore facilities.

Now Delfin is asking FERC to extend that for another four years by September 28, 2027.

Delfin said that the offtake contracts already executed “amply support” FID for its first floating LNG producer.

Based on additional ongoing negotiations, Delfin expects that the FID for its second FLNG will follow “soon” after the first.

Delfin expects to announce “very soon” its agreement with major infrastructure investors to provide the needed equity for its first two FLNGVs and has begun discussions with a consortium of banks (led by Delfin’s financial advisor Citigroup) to provide the project debt financing, it said.

Furthermore, Delfin LNG has not only completed the FEED for the FLNG construction with South Korea’s Samsung Heavy Industries and US engineer Black & Veatch, but also has negotiated a binding engineering, construction and procurement contract with those counterparts that is expected to be executed by September this year, the firm said.

Delfin has been in active discussions with MARAD and the US Coast Guard concerning satisfaction of the conditions of the MARAD ROD and expects the issuance of its final deepwater port license “soon” as well.

“Given all this significant progress, Delfin LNG is confident that it is nearing FID on its first FLNGV and expects the FID to occur this October,” it said.

“Accordingly, Delfin LNG respectfully urges the Commission to act on this request expeditiously and to grant the requested extension prior to the current condition deadline of September 28, 2023, to facilitate the expected FID in October,” the firm said.

Most Popular

Excelerate says purchased LNG carier set for FSRU conversion

US FSRU player Excelerate Energy confirmed on Monday that its recently purchased LNG carrier Excelerate Shenandoah is the company's first FSRU conversion candidate.

Excelerate working to expand Jamaican LNG business

US FSRU player Excelerate Energy has already made some smaller investments to further optimize its recently acquired LNG business in Jamaica, according to CEO Steven Kobos.

Venture Global wins Calcasieu Pass arbitration against Shell

US LNG exporter Venture Global LNG has won an arbitration case against UK-based LNG giant Shell over LNG sales from the Calcasieu Pass plant in Louisiana.

More News Like This

Venture Global to introduce gas to 16th Plaquemines LNG block

US LNG exporter Venture Global LNG is seeking approval from the US FERC to introduce natural gas to the sixteenth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

Glenfarne still expects Texas LNG FID by end of this year

US energy firm Glenfarne confirmed it is targeting a final investment decision on its planned 4 mtpa Texas LNG export project in the port of Brownsville by the end of 2025 after the US FERC issued the final supplemental environmental impact statement for the project.

Venture Global’s Plaquemines LNG to commission fourth tank

US LNG exporter Venture Global LNG has received approval from the US FERC to commission the fourth storage tank with LNG at its Plaquemines plant in Louisiana.

US FERC issues final SEIS for NextDecade’s Rio Grande LNG project

The US Federal Energy Regulatory Commission (FERC) has released a final supplemental environmental impact statement for NextDecade's Rio Grande LNG facility and the accompanying pipeline in Texas. FERC continues to conclude that approval of the projects would result in "less than significant impacts."