Delfin seeks more time to build its US floating LNG export project

Delfin LNG, a unit of Delfin Midstream and the developer of a floating LNG export project in the Gulf of Mexico, has requested more time from US FERC to put into service the project’s onshore facilities in Louisiana.

The firm revealed this in a letter to US FERC seeking an additional one-year extension to construct, operate and maintain certain onshore metering, compression, and piping facilities until September 2023.

The facilities would transport and deliver natural gas to Delfin’s deepwater port in federal waters offshore Louisiana.

Delfin plans to install up to four self-propelled FLNG vessels that could produce up to 13 mtpa of LNG or 1.7 billion cubic feet per day of natural gas.

This is the fourth time Delfin has asked FERC for an extension to build the facilities.

However, this request follows a $3 billion long-term deal to supply liquefied natural gas to a unit of energy trader Vitol.

Under the SPA, Delfin will supply 0.5 million tonnes per annum on a free on-board (FOB) basis at its deepwater port to Vitol for a 15-year period.

In addition to the SPA, Vitol has completed a strategic investment in the company.

Delfin seeks more time to build its US floating LNG export project
Image: Delfin LNG

Besides the Vitol deal, Delfin has entered into term sheets or heads of agreement with other LNG off-takers.

The firm told FERC it expects to finalize these deals “soon”.

In addition to this commercial progress, Delfin has completed FEED with Samsung Heavy Industries and Black & Veatch for the construction of the units. The firm has recently
conducted meetings with MARAD, and the US Coast Guard, concerning compliance with the
conditions of its deepwater port authorization as well.

As a modular project consisting of four separate floating LNG vessels, Delfin requires only 2 to 2.5 mtpa of long-term off-take contracts to support a final investment decision and begin construction of its project.

“Given all this significant progress, Delfin LNG is on schedule to make FID on its first FLNGV by the end of this year,” it said.

Most Popular

GTT opens Qatar office

French LNG containment giant GTT has opened a new office in Doha, Qatar's capital and economic hub. GTT’s chairman Philippe...

Eni’s FLNG launched in China

According to separate statements by Eni and WNE, the launching of the hull took place on Saturday. In Congo's Lingala...

CoolCo seeks long-term employment for two LNG carriers

In August, Coolco said it plans to employ its first newbuild LNG vessel, Kool Tiger, on a shorter deal...

More News Like This

Venture Global moving forward with Plaquemines LNG commissioning

The regulator said in a filing dated November 6 that it grated Venture Global Plaquemines LNG's request to commission...

Golden Pass secures three-year extension to complete Texas LNG terminal

Under the original FERC order from 2016, Golden Pass LNG was required to complete and place into service the...

Cheniere’s Corpus Christi expansion project nears launch of LNG production

"Together with Bechtel, we continue to advance our Corpus Christi Stage 3 project ahead of schedule and anticipate achieving...

Venture Global’s Plaquemines LNG to commission fourth liquefaction block with nitrogen

According to a filing, the regulator approved the commissioning of the block on October 16. The FERC granted the commissioning...