Equinor’s Hammerfest LNG plant to remain offline until May 27

Equinor’s 4.3 mtpa Hammerfest LNG export plant in Norway is now expected to be offline until May 27 due to a compressor failure, according to data by Gassco.

LNG Prime reported on May 5, citing data from Gassco, that the event has started on May 4 with an expected restart date of May 19.

However, Gassco’s data now shows that the outage has been extended for six more days.

It said that all of the 18.4 mcm/day (6.5 bcm/year) capacity will not be available during the period until May 27.

Equinor started again shipping LNG from the Hammerfest terminal in June last year since a fire that broke out at the facility in September 2020.

Hammerfest LNG liquefies natural gas coming from the Snohvit field in the Barents Sea.

Gas reaches Hammerfest LNG via a 160-kilometer gas pipeline which became operational in the autumn of 2007.

The firm and its partners are also upgrading the plant.

Equinor is the operator of both the Snohvit field and Hammerfest LNG with a 36.8 percent stake.

Other license owners of Snohvit are Petoro (30 percent), TotalEnergies EP Norge (18.4 percent), Neptune Energy Norge (12 percent), and Wintershall Dea Norge (2.81 percent).

Most Popular

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

Amigo LNG, Sahara seal 20-year SPA

Amigo LNG, a unit of LNG Alliance, has signed a 20-year sales and purchase agreement with Sahara Group to supply the latter with liquefied natural gas from its planned 7.8 mtpa LNG export plant in Mexico.

LNG shipping rates continue to decrease

Spot LNG freight shipping rates in both basins continued to decrease this week, while European prices increased compared to last week.

More News Like This

Norway’s Equinor restarts Hammerfest LNG export plant

Gassco data showed on Monday that the unplanned shutdown event ended on Sunday. A spokeswoman for Equinor also confirmed the...

Equinor extends shutdown of Hammerfest LNG export plant

Equinor decided to stop production on January 2 due to an issue on a compressor which reinjects CO2 to...

Norway’s Equinor shuts Hammerfest LNG terminal

Gassco data showed on Thursday that Hammerfest LNG will be offline until January 9, 2025. LNG Prime invited Equinor to...

Northern Lights welcomes second LNG-powered LCO2 carrier in its fleet

The second Northern Lights JV’s LNG-powered liquefied CO2 carrier has been delivered in China. Northern Lights, the JV consisting of...