Freeport LNG gets OK to start commissioning second jetty

Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant in Texas, has secured approval from the US FERC to start commissioning its second jetty.

In February this year, the LNG terminal operator shipped the first cargo from its LNG export plant in Texas since the shutdown in June 2022.

Freeport LNG received approvals from both FERC and PHMSA during the first quarter to restart Phase I operations.

These consist of three trains, two LNG storage tanks (tanks 1 and 2), and a single LNG jetty (dock 1).

However, these approvals did not grant Freeport LNG to commission or place LNG tank 3, loop 2, and dock 2 back into service.

In order to continue Freeport’s sequential plan to return the export facility to full commercial operations, Freeport recently requested approval from FERC for the nitrogen cooldown of the loop 2 LNG rundown piping system and the introduction of hydrocarbons to loop 2 to complete its cooldown and commissioning.

FERC said in filling dated October 27 that it has granted Freeport LNG’s request to start “commissioning, including cooldown, of Loop 2 LNG transfer piping, Dock 2, and the 8-inch LNG recirculation piping.”

The regulator said additional authorization to restart operations is necessary to reinstate service for loop 2 LNG circulation to enable ship loading to dock 2.

“Authorization will only be granted following the review of filed responses, a determination that the facilities are fit for service, and documentation that acceptable measures have been put into place to safely return the facilities to operation,” it said.

FERC also noted that Freeport LNG must also comply with any applicable PHMSA and US Coast Guard requirements.

Most Popular

NFE says Altamira LNG offline due to mechanical issue

New Fortress Energy's Fast LNG (FLNG) project off Mexico’s Altamira is offline due to a mechanical issue with the facility’s gas turbine.

Karpowership awards new FSRU conversion job to Seatrium

Singapore’s Seatrium will convert another LNG carrier into a floating storage and regasification unit for Turkiye’s Karpowership under a new contract.

Botas seeks LNG carrier charter

Turkiye’s state-owned natural gas and LNG firm Botas has launched a tender to charter a liquefied natural gas (LNG) carrier for a firm 940-day period.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project 55.6 percent complete

US LNG exporter Cheniere continues to progress construction on its Corpus Christi Midscale Trains 8 and 9 project in Texas.

Venture Global seeks FERC OK to place first Plaquemines LNG phase in service

Venture Global's Plaquemines LNG is seeking approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

NextDecade’s Rio Grande LNG gets FERC OK to boost capacity

US LNG developer NextDecade has secured a green light from the Federal Energy Regulatory Commission to increase approved capacity at its Rio Grande LNG terminal in the Port of Brownsville, Texas.

US FERC issues final EIS for Cheniere’s Sabine Pass expansion project

The US Federal Energy Regulatory Commission (FERC) has released a final environmental impact statement for Cheniere’s planned Sabine Pass Stage 5 expansion project. The regulator confirmed that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”