Freeport seeks FERC OK to start introducing LNG to piping system

Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant in Texas, has asked the US FERC for approval to start introducing LNG into the piping system at the plant. The terminal has been offline for some seven months due to an incident that took place on June 8 last year.

According to a FERC filling dated January 22, Freeport has completed all repairs needed to restart the export facility on Quintana Island.

Freeport is requesting authorization to cool down the Loop 1 LNG transfer piping and and reinstate the facility’s boil off gas (BOG) management compressors and associated piping as its initial step to resuming normal operations at the export facility.

The LNG terminal operator delayed the restart of the plant several times and in the latest update issued in December, Freeport said it planned the initial restart of its liquefaction facility in the second half of January 2023.

Freeport must obtain written approval from FERC before restarting any non-emergency operations in existing facilities, and commissioning and placing any facilities back into service.

More approvals needed

Freeport said in the filling that cool down of the Loop 1 LNG transfer piping includes the “slow and deliberate introduction of LNG into the piping system to allow the piping to cool down to cryogenic temperatures necessary for circulation of LNG within the Loop 1 piping system and to transfer LNG to Dock 1 of the export facility.”

According to the LNG terminal operator, it would perform LNG cool down “slowly and methodically over a period of approximately 11 days to ensure that the temperature rate change does not exceed thermal shock tolerances.”

As a result of the cooldown, BOG production within the facility will increase as the movement of cold vapor and subsequently, LNG increases.

“As opposed to directing this increased BOG production to the facility flare, the BOG can be routed to the facility BOG management compressors and transported via pipeline to the upstream pretreatment facility for use as fuel gas,” it said.

The firm asked FERC to respond to this request by January 24.

Also, Freeport would need subsequent approvals to start Loop 1 LNG circulation and ship loading to Dock 1, as well as to start returning the liquefaction trains to operation, it said.

BP, Jera, Osaka Gas, SK E&S, as well as TotalEnergies have long-term contracts with Freeport LNG.

Besides the three trains, Freeport LNG is also planning to add another production unit with a capacity of 5 mtpa, but it has not yet taken a final investment decision.

In October, US energy regulators granted Freeport LNG’s request for a 26-month extension of time to build the fourth liquefaction train.

Most Popular

BP, Venture Global to supply LNG to Bulgargaz in January and February

Bulgargaz previously sought two LNG cargoes for delivery during January and February 2025. The company recently announced that 19 international...

Geocean kicks off work on Congo FLNG mooring project

French marine and offshore contractor, Geocean, a VINCI Construction Grands Projets unit, has started working on a new contract...

Petronas, CNPC strengthen LNG ties

Malaysia's Petronas and China National Petroleum Corporation (CNPC) signed a memorandum of understanding (MoU) to strengthen collaboration in various...

More News Like This

Venture Global moving forward with Plaquemines LNG commissioning

The regulator said in a filing dated November 6 that it grated Venture Global Plaquemines LNG's request to commission...

Golden Pass secures three-year extension to complete Texas LNG terminal

Under the original FERC order from 2016, Golden Pass LNG was required to complete and place into service the...

Cheniere’s Corpus Christi expansion project nears launch of LNG production

"Together with Bechtel, we continue to advance our Corpus Christi Stage 3 project ahead of schedule and anticipate achieving...

Venture Global’s Plaquemines LNG to commission fourth liquefaction block with nitrogen

According to a filing, the regulator approved the commissioning of the block on October 16. The FERC granted the commissioning...