Gastrade: Greece’s first FSRU to start commercial ops by end of April

Greece’s Gastrade expects to launch commercial operations at its FSRU-based LNG import terminal off Alexandroupolis by the end of April.

The 2018-built 174,000-cbm LNG carrier, GasLog Hong Kong, delivered on February 18 a commissioning cargo from the US to the 153,600-cbm Alexandroupolis.

The LNG carrier, chartered by France’s TotalEnergies, brought the shipment from Sempra’s Cameron LNG plant in Louisiana.

Following completion of the ship-to-ship LNG transfer, GasLog Hong Kong left the FSRU on February 27, a spokeswoman for Gastrade told LNG Prime on Thursday.

“At this time, a second cargo for commissioning purposes is not expected,” the spokeswoman said.

“If no major issues arise during the commissioning, the project will reach commercial operations by the end of April 2024,” she said.

Greece’s DEPA, who is a Gastrade shareholder, previously said that it brought the commissioning cargo to the FSRU.

Besides DEPA, Gastrade’s shareholders include founder Copelouzou, DESFA, Bulgartransgaz, and GasLog.

Greece’s first FSRU arrived in Alexandroupolis from Singapore on December 17 and mooring hook-up was completed on December 23, 2023.

The FSRU is located in the sea of Thrace at a distance of 17.6 km SW from the port of Alexandroupolis and 10 km from the nearest coast of Makri. Also, it is connected to a high-pressure subsea and onshore gas transmission pipeline.

Once operational, the pipeline will deliver natural gas to the Greek transmission system and onwards to the final consumers in Greece, Bulgaria, Romania, North Macedonia, Serbia and further to Moldova and Ukraine to the East and Hungary and Slovakia to the West, Gastrade said.

The Alexandroupolis LNG terminal will have a capacity of 5.5 Bcm.

This is Greece’s second LNG import facility, adding to DESFA’s import terminal located on the island of Revithoussa.

Most Popular

Woodside updates on Louisiana LNG construction work

Australian LNG producer Woodside has released the latest construction update for the first phase of its Louisiana LNG project.

Shell’s LNG Canada set to receive LNG cargo as part of commissioning activities

Shell’s LNG Canada is set to receive a cargo of liquefied natural gas onboard the 173,400-cbm LNG carrier, Maran Gas Roxana, as part of the commissioning and start-up phase, a spokesman for LNG Canada told LNG Prime.

HD Hyundai Samho kicks off work on Nakilat’s LNG carrier

South Korean shipbuilder HD Hyundai Samho has officially started building Nakilat’s first of two LNG carriers as part of an order placed last year.

More News Like This

GasLog Partners reports lower profit in Q4

GasLog Partners, part of Greek LNG carrier owner GasLog, reported lower profit and revenues in the fourth quarter of the last year due to a weak market and a non-cash impairment loss.

Gastrade: Alexandroupolis FSRU remains offline due to technical issue

"For the moment, regasification services have been suspended due to a technical issue, for which we will provide further...

BP delivers US LNG cargo to Bulgargaz via Alexandroupolis FSRU

The 2021-built 174,000-cbm, BW Lesmes, delivered the shipment to the 153,500-cbm FSRU, Alexandroupolis, on January 19, a spokeswoman for...

Greek LNG imports drop in 2024

The Greek gas grid and LNG terminal operator said Revithoussa LNG shipments in 2024 totaled 18.69 terawatt hours (TWh)...