Gasunie’s Eemshaven LNG hub to resume gas supplies to Dutch grid on February 6

Dutch natural gas firm Gasunie is now planning to resume sendout to the grid from its LNG import hub in the port of Eemshaven on February 6.

A Gasunie spokeswoman told LNG Prime last week that the work on the heat connection would take longer than expected and the firm planned to resume sendout to the grid by the end of this week.

Gasunie previously said it would not be able to send natural gas from the terminal to the grid during January 13-30 due to an outage at RWE.

RWE operates a power plant in the port of Eemshaven which supplies heat to the terminal.

“We have been informed by RWE that additional time is needed to carry out the technical work for the connection of the heat pipeline,” the spokeswoman said in emailed comment on Wednesday.

“This changes the planning. We now expect to start up this Friday, February 3, after which the first gas can be sent out again on Monday, February 6,” the spokeswoman said.

Full capacity on March 1

Gasunie expects to reach full operations at the LNG hub on March 1.

However, both of these schedules depend on the completion of the work, the spokeswoman noted.

The facility operated by Gasunie’s EemsEnergyTerminal features two chartered FSRUs and they include the 26,000-cbm barge-based FSRU Eemshaven LNG and the 170,000-cbm Energos Igloo.

The heat connection is needed as sea water is too cold during this time of the year to be used for the regasification process.

Gasunie’s new terminal with a capacity of about 8 bcm per year started delivering regasified LNG to the Dutch grid in September and has up to date received eleven cargoes.

Shell previously booked 4 bcm while Czech utility CEZ took 3 bcm of the Eemshaven terminal’s total capacity. France’s Engie secured the remaining 1 bcm of capacity.

Most Popular

China’s gas imports continue to rise

Natural gas imports during the last month reached about 11.99 million tonnes, rising 18.2 percent compared to 10.14 million tonnes...

PetroVietnam Gas to supply LNG to EVN’s power plant

According to separate statements by PV Gas and EVN, the duo signed the MoU on October 4. The deal includes...

Adnoc Gas drops plan to upgrade Das Island LNG export terminal

"While not proceeding with the LNG2.0 project, we will continue to invest in Das Island, particularly as it remains...

More News Like This

Dutch Gate gets first cargo from NFE’s Altamira LNG terminal in Mexico

The 138,000-cbm Energos Princess delivered the maiden cargo from Altamira to the LNG terminal owned by Gasunie and Vopak. Energos...

FID taken on German onshore LNG terminal

"The FID was taken within the last two weeks," a spokesman for German LNG Terminal told LNG Prime on...

Gasunie, RWE plan to launch German onshore LNG terminal in 2027

In 2022, Gasunie joined forces with the German government and RWE to build the LNG import terminal, which is worth about...

Dutch Gate LNG terminal launches two truck loading bays

The fourth and the fifth bays add to the three truck loading bays at the LNG hub owned by...