LNG exports from the Gladstone port in Australia’s Queensland were almost flat in August compared to the same month last year, according to the monthly data by Gladstone Ports Corporation.

Curtis Island is home to the Santos-operated GLNG plant, the ConocoPhillips-led APLNG terminal, and Shell’s QCLNG facility. These are the only LNG export facilities on Australia’s east coast.

Last month, about 1,836 million tonnes of LNG or 28 cargoes left the three Gladstone terminals on Curtis Island.

This compares to 1,837 million tonnes or 29 cargoes in August 2022, the data shows.

August LNG exports rose by about 1.9 percent compared to the previous month when LNG exports reached some 1,802 million tonnes of LNG or 27 cargoes.

Moreover, most of August LNG exports, or 1,104 million tonnes, landed in China, marking a rise of 19.8 percent compared to 922,050 tonnes last year.

Volumes to South Korea dropped to 241,598 tonnes from 285,929 tonnes last year, while volumes to Malaysia decreased slightly to 244,274 tonnes last month from 248,015 tonnes last year.

GPC also reported that 116,694 tonnes of LNG were sent to Singapore, 67,400 tonnes were sent to the Philippines, and 62,383 tonnes were sent to Japan.

Volumes to Singapore decreased from 128,056 tonnes in August last year, while volumes to Japan dipped from 253,742 tonnes last year.

Most Popular

Golar moving forward with new FLNG order

Floating LNG player Golar LNG is moving forward with its plans to order its fourth FLNG conversion. In order to secure "attractive" delivery, Golar plans to enter into slot reservations for long-lead equipment within the third quarter of this year.

Venture Global eyes FID on second CP2 phase in 2026

US LNG exporter Venture Global LNG expects to make a final investment decision on the second phase of its CP2 LNG project in Louisiana in 2026, according to CEO Mike Sabel.

AG&P LNG inks offtake MoU for Australian LNG import project

Nebula Energy’s AG&P LNG said it had signed a memorandum of understanding with an Australian integrated energy provider under which the latter may become a significant offtaker of the proposed Outer Harbor LNG terminal in South Australia.

More News Like This

Origin reports steady APLNG revenue

The Australia Pacific LNG project logged steady revenues in the fiscal year ending June 30 from the prior year, mainly due to higher LNG volumes as the plant operated well above nameplate capacity following the LNG vessel power outage incident in the prior year, according to shareholder Origin Energy.

Gladstone LNG exports climb in July

Liquefied natural gas (LNG) exports from the Gladstone port in Australia’s Queensland rose in July compared to the same month last year, according to the monthly data by Gladstone Ports Corporation.

Santos says Barossa project 97 percent complete

The Barossa gas project, which will supply feed gas to the Santos-operated Darwin LNG plant, is 97 percent complete and remains on target for first production in the third quarter of 2025, according to Australia's Santos.

Monadelphous scores new LNG contracts

Australian engineering firm Monadelphous has secured contracts for Shell's Crux natural gas project offshore Western Australia and the Australia Pacific LNG project in Queensland.