Kosmos says BP’s Tortue FLNG project slightly delayed

The first phase of BP’s Greater Tortue Ahmeyim FLNG development offshore Mauritania and Senegal will be slightly delayed, according to project partner Kosmos Energy.

Dallas-based Kosmos said on Tuesday the project partners have received a revised forecast from the EPCIC contractor, TechnipFMC. The contractor said that COSCO Shipping’s Qidong yard would likely deliver the FPSO later than planned.

This is due to “labor shortages at the COSCO yard in China following a ramp up in activity at the shipyard as the pandemic recedes,” Kosmos said.

Kosmos said the partners expect this would delay the project for about three months, pushing the timing of first gas to the third quarter of 2023.

BP, as operator of the project, has informed partners that costs would probably increase due to the impacts of Covid-19, including the FPSO delay, cost inflation and scope growth, the firm said.

On the basis of the revised schedule, Kosmos currently expects the gross cost for the project to be about 15% higher, resulting in an estimated increase of Phase 1 costs to first gas net to Kosmos of around $100 million, coming primarily in 2023.

Moreover, Kosmos expects the FPSO sale and lease back transaction to close this quarter upon the finalization of the documentation between the governments and partners.

Following the closing of the transaction, the company will work to complete the refinancing of the National Oil Company loans, Kosmos said.

Second phase FID

In addition, the project partners continue to make progress on the second phase of the LNG project with a final investment decision targeted for late 2022, the firm said.

The Tortue/Ahmeyim gas field, located offshore on the border between Mauritania and Senegal, has about 15 trillion cubic feet of gas, according to BP.

The FPSO will process the gas, removing heavier hydrocarbon components, prior to delivering it to a floating LNG provider which will sit nearshore a hub.

Besides operator BP and Kosmos, the project includes national oil companies Petrosen and SMHPM.

Furthermore, Singapore’s Keppel shipyard is currently converting Golar’s Gimi FLNG for the project. BP and Golar agreed on a one-year delay for the unit last year due to the Covid-19 coronavirus pandemic.

The yard should deliver the FLNG in 2023.

Once deployed offshore Mauritania and Senegal, it would provide about 2.5 million tonnes of LNG per annum on average.

Most Popular

Venture Global’s Plaquemines LNG terminal achieves first production

Venture Global announced on Friday it had reached first LNG production at the company’s second facility, Plaquemines LNG, in...

Spot LNG rates remain weak

“Spark30S rates rose for a fourth consecutive week, increasing marginally by $750 to $23,500 per day,” Qasim Afghan, Spark’s commercial...

Swan Energy, Nebula’s AG&P LNG plan Indian JV

Swan Energy said on Friday it had signed a heads of agreement with AG&P Terminals &Logistics (Singapore). The two firms...

More News Like This

BP and Adnoc launch new Egyptian JV

Announced in February 2024, Arcius Energy is 51 percent owned by BP and 49 percent by XRG, Adnoc's investment...

BP appoints new LNG trading head

Milongo announced on Tuesday during the World LNG Summit and Awards in Berlin that he had recently been appointed...

Worley secures BP contract extension in Oman

Under the three-year contract extension, the JV will continue to provide engineering, procurement, and construction (EPC) services to BP’s...

Saipem consortium clinches $1.2 billion Tangguh UCC contract

The EPCI contract is part of the BP Berau-led integrated project known as Tangguh UCC, comprising of Ubadari field...