LNG Canada pipeline 80 percent complete, costs continue to rise

TC Energy’s Coastal GasLink project, which will supply natural gas to the Shell-led LNG Canada export terminal, is progressing with the construction of the pipeline in British Columbia while costs continue to rise.

Coastal GasLink said in a statement on November 29 that the pipeline was 80 percent complete. The overall progress reached about 75 percent in September and in October about 77.6 percent.

To date, Coastal GasLink has installed more than 470 km of pipe across the 670-km route, according to the firm.

Cumulatively, the company’s team has spent 38 million hours working on this project, with more than 6,000 people employed at its peak, it said.

The pipeline has the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023.

Costs to rise further

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said this week that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

“We continue to face significant cost pressures in Western Canada relating to labor costs and shortages of skilled labor, along with contractor underperformance and disputes. The project has also been impacted by other unexpected events including drought conditions, and erosion and sediment control challenges,” the firm said.

TC Energy said it would provide an updated capital cost estimate in early-2023 that would incorporate the scope of recent developments.

As per the LNG Canada plant in Kitimat, the project is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Coastal Bend LNG plans large Texas export plant

Coastal Bend LNG said it had initiated development of a 22.5 million ton per annum (mtpa) natural gas liquefaction and export facility on the Texas Gulf Coast.

Golden Pass LNG contractors agree terms for second and third train

Japan's Chiyoda and US-based McDermott have signed a binding term sheet with Golden Pass LNG, a joint venture owned by QatarEnergy and ExxonMobil, to complete the construction of the second and third liquefaction units at the giant LNG export plant in Texas.

HD Hyundai Samho scores contract to build LNG carrier quartet

South Korea’s HD Hyundai Samho has secured an order to build four liquefied natural gas (LNG) carriers for about $1.03 billion.

More News Like This

Shell’s LNG Canada achieves first LNG

LNG giant Shell has started production at the first liquefaction train at its LNG Canada export terminal in Kitimat, an LNG Canada spokesperson told LNG Prime on Sunday.

Shell’s LNG Canada nears first LNG

LNG giant Shell is nearing the launch of the first liquefaction train at its LNG Canada export terminal in Kitimat.

CFO: Shell on track to ship first LNG Canada cargo in middle of 2025

LNG giant Shell remains on track to deliver the first liquefied natural gas cargo from its LNG Canada export terminal in Kitimat in the middle of this year, according to Shell's finance chief, Sinead Gorman.

Chris Cooper takes over as LNG Canada CEO

Chris Cooper has taken over as president and chief executive officer of LNG Canada as the Shell-led JV prepares to ship the first LNG cargoes from the Kitimat facility.