LNG Canada pipeline 80 percent complete, costs continue to rise

TC Energy’s Coastal GasLink project, which will supply natural gas to the Shell-led LNG Canada export terminal, is progressing with the construction of the pipeline in British Columbia while costs continue to rise.

Coastal GasLink said in a statement on November 29 that the pipeline was 80 percent complete. The overall progress reached about 75 percent in September and in October about 77.6 percent.

To date, Coastal GasLink has installed more than 470 km of pipe across the 670-km route, according to the firm.

Cumulatively, the company’s team has spent 38 million hours working on this project, with more than 6,000 people employed at its peak, it said.

The pipeline has the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023.

Costs to rise further

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said this week that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

“We continue to face significant cost pressures in Western Canada relating to labor costs and shortages of skilled labor, along with contractor underperformance and disputes. The project has also been impacted by other unexpected events including drought conditions, and erosion and sediment control challenges,” the firm said.

TC Energy said it would provide an updated capital cost estimate in early-2023 that would incorporate the scope of recent developments.

As per the LNG Canada plant in Kitimat, the project is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Eni: third phase of YPF’s Argentina LNG project requires $20 billion investment

The third phase of YPF's Argentina LNG export project would require an investment of about $20 billion, according to Eni’s COO of global natural resources, Guido Brusco.

Wison scores Suriname FLNG gig

China’s Wison New Energies has signed a detailed feasibility study deal for a newbuild floating liquefied natural gas (FLNG) facility in Suriname's offshore Block 52.

Venture Global to introduce gas to tenth Plaquemines liquefaction block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the tenth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Chris Cooper takes over as LNG Canada CEO

Chris Cooper has taken over as president and chief executive officer of LNG Canada as the Shell-led JV prepares to ship the first LNG cargoes from the Kitimat facility.

Update: Shell’s LNG Canada receives LNG cargo

Shell’s LNG Canada has received a cargo of liquefied natural gas as part of the commissioning and start-up phase.

Shell’s LNG Canada set to receive LNG cargo as part of commissioning activities

Shell’s LNG Canada is set to receive a cargo of liquefied natural gas onboard the 173,400-cbm LNG carrier, Maran Gas Roxana, as part of the commissioning and start-up phase, a spokesman for LNG Canada told LNG Prime.

Shell’s LNG Canada moving forward with commissioning activities

Shell’s LNG Canada is moving forward with its commissioning and start-up phase and expects to receive a liquefied natural gas (LNG) cargo soon.