LNG Canada pipeline 80 percent complete, costs continue to rise

TC Energy’s Coastal GasLink project, which will supply natural gas to the Shell-led LNG Canada export terminal, is progressing with the construction of the pipeline in British Columbia while costs continue to rise.

Coastal GasLink said in a statement on November 29 that the pipeline was 80 percent complete. The overall progress reached about 75 percent in September and in October about 77.6 percent.

To date, Coastal GasLink has installed more than 470 km of pipe across the 670-km route, according to the firm.

Cumulatively, the company’s team has spent 38 million hours working on this project, with more than 6,000 people employed at its peak, it said.

The pipeline has the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023.

Costs to rise further

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said this week that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

“We continue to face significant cost pressures in Western Canada relating to labor costs and shortages of skilled labor, along with contractor underperformance and disputes. The project has also been impacted by other unexpected events including drought conditions, and erosion and sediment control challenges,” the firm said.

TC Energy said it would provide an updated capital cost estimate in early-2023 that would incorporate the scope of recent developments.

As per the LNG Canada plant in Kitimat, the project is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Glenfarne still expects Texas LNG FID by end of this year

US energy firm Glenfarne confirmed it is targeting a final investment decision on its planned 4 mtpa Texas LNG export project in the port of Brownsville by the end of 2025 after the US FERC issued the final supplemental environmental impact statement for the project.

Kosmos: Tortue FLNG to hit full capacity in Q4

UK-based energy giant BP and its partners expect the 2.7 mtpa Golar FLNG Gimi, which serves the Greater Tortue Ahmeyim LNG project offshore Mauritania and Senegal, to reach its nameplate capacity in the fourth quarter of this year, according to US-based Kosmos Energy.

Equinor’s Hammerfest LNG back online after maintenance

Norwegian energy firm Equinor has resumed operations at its 4.3 mtpa Hammerfest LNG export plant following an extended maintenance shutdown, a spokesperson for Equinor told LNG Prime on Monday.

More News Like This

Fluor, JGC score FEED job for LNG Canada expansion

A joint venture of US engineer Fluor and Japan's JGC has been awarded the contract to update the front-end engineering and design (FEED) for a proposed Phase 2 expansion of the Shell-led LNG Canada project.

Shell CEO says LNG Canada ramp-up in line with expectations

LNG Canada's production ramp-up is "very much" in line with what Shell had expected, according to Shell CEO Wael Sawan.

South Korea gets first LNG Canada cargo

The 174,000-cbm GasLog Glasgow, which is carrying the first liquefied natural gas cargo produced at the Shell-led LNG Canada facility in Kitimat, has arrived in Tongyeong, South Korea, according to shipping data.

LNG Canada to send third cargo

Shell-led LNG Canada is expected to soon ship the third cargo of liquefied natural gas from the Kitimat facility, according to shipping data.