LNG Canada pipeline achieves 100 percent pipe installation

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, has achieved 100 percent pipe installation across the entire project route.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the “final ‘Golden Weld’ took place at the base of Cable Crane Hill in Section 8 West earlier this month.”

This milestone means that all 670 kilometers of pipe has been welded, coated, lowered into the trench, rigorously tested, and backfilled, it said.

“From the Wilde Lake compressor station near Dawson Creek to our metering station in Kitimat, physical construction on the project is now complete,” it said.

“The work is the last step before mechanical completion which is well on track for our year-end target and advances Coastal GasLink as Canada’s first direct path for LNG to international markets,” the firm said.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Seapeak books $19.3 million charge as it lays off seafarers on steam LNG carriers

Stonepeak’s Seapeak booked $19.3 million of restructuring charges in the second quarter of this year, primarily due to laying off its Spanish seafarers working on steam LNG carriers.

Golar moving forward with new FLNG order

Floating LNG player Golar LNG is moving forward with its plans to order its fourth FLNG conversion. In order to secure "attractive" delivery, Golar plans to enter into slot reservations for long-lead equipment within the third quarter of this year.

Hanwha’s units, Kospo to jointly buy US LNG

South Korea's Hanwha Aerospace and Hanwha Energy, units of Hanwha, are teaming up with compatriot Korea Southern Power (Kospo) to jointly buy US liquefied natural gas (LNG) supplies.

More News Like This

Fluor, JGC score FEED job for LNG Canada expansion

A joint venture of US engineer Fluor and Japan's JGC has been awarded the contract to update the front-end engineering and design (FEED) for a proposed Phase 2 expansion of the Shell-led LNG Canada project.

Shell CEO says LNG Canada ramp-up in line with expectations

LNG Canada's production ramp-up is "very much" in line with what Shell had expected, according to Shell CEO Wael Sawan.

South Korea gets first LNG Canada cargo

The 174,000-cbm GasLog Glasgow, which is carrying the first liquefied natural gas cargo produced at the Shell-led LNG Canada facility in Kitimat, has arrived in Tongyeong, South Korea, according to shipping data.

LNG Canada to send third cargo

Shell-led LNG Canada is expected to soon ship the third cargo of liquefied natural gas from the Kitimat facility, according to shipping data.