LNG Canada pipeline achieves 100 percent pipe installation

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, has achieved 100 percent pipe installation across the entire project route.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the “final ‘Golden Weld’ took place at the base of Cable Crane Hill in Section 8 West earlier this month.”

This milestone means that all 670 kilometers of pipe has been welded, coated, lowered into the trench, rigorously tested, and backfilled, it said.

“From the Wilde Lake compressor station near Dawson Creek to our metering station in Kitimat, physical construction on the project is now complete,” it said.

“The work is the last step before mechanical completion which is well on track for our year-end target and advances Coastal GasLink as Canada’s first direct path for LNG to international markets,” the firm said.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

- Advertisements -

Most Popular

Golden Pass LNG to ramp up construction activities after Zachry deal

QatarEnergy and ExxonMobil will ramp up construction activities at the Golden Pass LNG export terminal in Texas after a...

Tellurian updates on Driftwood LNG work

US LNG terminal developer Tellurian, which is being acquired by Australia's Woodside, released the latest construction update for the...

Hudong-Zhonghua confirms TotalEnergies order for LNG bunkering vessel

China’s Hudong-Zhonghua said it had secured an order to build one 18,600-cbm LNG bunkering vessel for French energy giant...

More News Like This

Fluor and JGC move one step closer to completion of LNG Canada’s first train

US engineer Fluor announced completion of the final weld on the first production train at the Shell-led LNG Canada...

Malaysia’s Petronas adds new vessels to its fleet as LNG Canada launch nears

Malaysian energy giant Petronas has added three new liquefied natural gas (LNG) carriers to its fleet as it prepares...

Ksi Lisims LNG partners to buy Prince Rupert pipeline project from TC Energy

Houston-based Western LNG and the Nisga’a Nation, the partners in Canada's Ksi Lisims LNG project, have agreed to buy...

Shell CEO: LNG Canada to start commissioning later this year

Shell’s LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities...