LNG Canada pipeline achieves 100 percent pipe installation

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, has achieved 100 percent pipe installation across the entire project route.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the “final ‘Golden Weld’ took place at the base of Cable Crane Hill in Section 8 West earlier this month.”

This milestone means that all 670 kilometers of pipe has been welded, coated, lowered into the trench, rigorously tested, and backfilled, it said.

“From the Wilde Lake compressor station near Dawson Creek to our metering station in Kitimat, physical construction on the project is now complete,” it said.

“The work is the last step before mechanical completion which is well on track for our year-end target and advances Coastal GasLink as Canada’s first direct path for LNG to international markets,” the firm said.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

- Advertisements -

Most Popular

Cedar LNG FID pushed back

Canada’s Pembina Pipeline and the Haisla Nation have again postponed a final investment decision on their Cedar floating LNG...

Eni to ship Congo’s first LNG cargo

Italy’s Eni will soon ship the first liquefied natural gas cargo from its Tango floating LNG facility moored in...

Hyundai Samho to build LNG carrier quartet for $1.08 billion

South Korea's Hyundai Samho has secured an order to build four liquefied natural gas (LNG) carriers for about $1.08...

More News Like This

Shell CEO: LNG Canada to start commissioning later this year

Shell’s LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities...

LNG Canada CEO: start-up activities will take more than a year to complete

Shell's LNG Canada project is now preparing to launch start-up activities next year and this program will take more...

HaiSea Marine takes delivery of its first LNG-powered tug

Turkey’s Sanmar has delivered the first of two LNG-powered tugs to Canada's HaiSea Marine, a joint venture majority owned...

Third LNG Canada electric tug delivered

HaiSea Marine’s third and final electric tugboat which will serve the Shell-led LNG Canada project is on its way...