LNG Canada pipeline achieves 90 percent completion

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, has achieved 90 percent overall completion.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in a construction update it still expects to complete the pipeline by the end of 2023.

Section 6, which stretches 63 kilometers from south of Burns Lake to south of Houston, achieved 100 percent pipe installation in June, marking the third of eight sections to complete pipe installation, following Sections 1 and 4 which achieved this milestone last year.

Coastal GasLink said it has completed mainline welding in Section 7, marking the final component of mainline welding across the project, while Section 5 has also completed all pipe installation with the exception of one remaining water crossing.

To date, 625 kilometers of pipe has been installed and nearly 97.5 percent of all pipe has been welded.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

Image: LNG Canada

As per the LNG Canada plant in Kitimat, the project built by JGC Fluor is more than 80 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Sempra advances Port Arthur LNG construction

US LNG exporter Sempra and compatriot Bechtel continue to make progress with construction work on the first phase of the Port Arthur LNG export terminal in Texas.

Another FSRU arrives in Egypt

The 160,000-cbm FSRU Energos Eskimo has arrived in Egypt from Jordan, according to shipping data. The unit is one of four FSRUs that will serve a charter deal with Egypt's EGAS as the country seeks to meet its growing demand for natural gas.

Steel cut for Cedar’s FLNG in South Korea

South Korea’s Samsung Heavy Industries has officially started building Cedar LNG's floating LNG production unit, which will be installed in Kitimat, on Canada’s West Coast.

More News Like This

CFO: Shell on track to ship first LNG Canada cargo in middle of 2025

LNG giant Shell remains on track to deliver the first liquefied natural gas cargo from its LNG Canada export terminal in Kitimat in the middle of this year, according to Shell's finance chief, Sinead Gorman.

Chris Cooper takes over as LNG Canada CEO

Chris Cooper has taken over as president and chief executive officer of LNG Canada as the Shell-led JV prepares to ship the first LNG cargoes from the Kitimat facility.

Update: Shell’s LNG Canada receives LNG cargo

Shell’s LNG Canada has received a cargo of liquefied natural gas as part of the commissioning and start-up phase.

Shell’s LNG Canada set to receive LNG cargo as part of commissioning activities

Shell’s LNG Canada is set to receive a cargo of liquefied natural gas onboard the 173,400-cbm LNG carrier, Maran Gas Roxana, as part of the commissioning and start-up phase, a spokesman for LNG Canada told LNG Prime.