LNG Canada pipeline achieves 90 percent completion

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, has achieved 90 percent overall completion.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in a construction update it still expects to complete the pipeline by the end of 2023.

Section 6, which stretches 63 kilometers from south of Burns Lake to south of Houston, achieved 100 percent pipe installation in June, marking the third of eight sections to complete pipe installation, following Sections 1 and 4 which achieved this milestone last year.

Coastal GasLink said it has completed mainline welding in Section 7, marking the final component of mainline welding across the project, while Section 5 has also completed all pipe installation with the exception of one remaining water crossing.

To date, 625 kilometers of pipe has been installed and nearly 97.5 percent of all pipe has been welded.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

Image: LNG Canada

As per the LNG Canada plant in Kitimat, the project built by JGC Fluor is more than 80 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Petrovietnam units plan new LNG-to-power project

PV Power and PV Gas, units of state-owned Petrovietnam, signed cooperation agreements to secure gas supplies for power plants in southwestern Vietnam and explore developing an integrated liquefied natural gas (LNG) project in the northern port city of Hai Phong.

Colombia’s Ecopetrol ditches LNG import tenders

Colombia’s state-owned energy firm Ecopetrol has rejected five-year liquefied natural gas (LNG) supply offers, saying that the minimum commercial conditions were not met.

Poland’s Gaz-System moves forward with Gdansk LNG jetty work

Poland’s state-owned LNG terminal operator, Gaz-System, is advancing construction of the jetty which will host the first floating storage and regasification unit (FSRU) for its LNG import project in Gdansk.

More News Like This

Canada backs Fort Simpson LNG power plant

The government of Canada is backing the construction of NTPC's new power plant in Fort Simpson that will primarily generate power using liquefied natural gas (LNG).

Tecnicas Reunidas scores LNG Canada pipeline gig

Shell-led LNG Canada has awarded a contract to Spanish engineering and construction firm Tecnicas Reunidas to provide EPCM services for the second phase of the Coastal GasLink pipeline in British Columbia, on Canada’s west coast.

First Nations invest in LNG Canada pipeline

Canada's TC Energy, operator of the LNG Canada pipeline, said it had closed an agreement with FN CGL Pipeline, an Indigenous-led investment entity representing five First Nations along the Coastal GasLink corridor.

Shell, partners take FID on LNG Canada Phase 2

UK-based LNG giant Shell and its LNG Canada partners have made a final investment decision on the project's second phase, which will double production capacity at the facility in Kitimat, British Columbia.