LNG Canada’s new tug berth to be completed in early 2024

A new tug berth being built for the Shell-led LNG Canada export project will be ready in early 2024 to welcome a fleet of dual-fuel and electric tugs.

Construction of the tug berth facility started in early 2023 and is scheduled to be fully completed in early 2024, LNG Canada said in a statement issued last week.

Bridgemans Kitamaat Joint Venture, a Haisla Nation partnership, has secured the new engineering, procurement, and construction contract award which includes the installation of marine piles, floating docks, and a breakwater.

LNG Canada says the new tug berth is essential to operation of the escort tugs and harbor tugs that will provide ship-assist and escort towing services to LNG carriers calling at LNG Canada’s export facility.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

LNG Canada's new tug berth to be completed in early 2024
Image: LNG Canada

HaiSea Marine, majority-owned by the Haisla Nation in partnership with Canada’s Seaspan ULC, has a major contract with LNG Canada to build and operate escort and harbor tugs required for the LNG export project worth more than $30 billion.

The new fleet of tugs will consist of two RAstar 4000-DF escort dual-fuel tugs that will run on LNG and also diesel.

Moreover, the fleet also includes three ElectRA 2800 electric tugs.

Turkey’s Sanmar is building the tugs designed by Vancouver BC-based naval architect company, Robert Allan.

Earlier this year, Sanmar launched the first of two LNG dual-fuel tugs that will feature Wartsila engines.

Also, Norway’s Corvus Energy won a contract to deliver batteries to the three electric tugs.

Most Popular

Venture Global’s Plaquemines LNG terminal achieves first production

Venture Global announced on Friday it had reached first LNG production at the company’s second facility, Plaquemines LNG, in...

Spot LNG rates remain weak

“Spark30S rates rose for a fourth consecutive week, increasing marginally by $750 to $23,500 per day,” Qasim Afghan, Spark’s commercial...

Swan Energy, Nebula’s AG&P LNG plan Indian JV

Swan Energy said on Friday it had signed a heads of agreement with AG&P Terminals &Logistics (Singapore). The two firms...

More News Like This

YPF, Shell seal Argentina LNG deal

YPF president and CEO Horacio Marin, and Shell's executive VP of LNG, Cederic Cremers,signed the deal in The Hague,...

Chevron-led JV secures GHG permit near Barrow Island

US energy giant Chevron and its partners Shell and ExxonMobil have been awarded the greenhouse gas (GHG) assessment permit...

Shell’s LNG Canada names new CEO

Cooper, currently LNG Canada’s senior vice president for Phase 1 pipeline and expansion will succeed Jason Klein as president...

Peru LNG terminal sent six cargoes in November

According to the shipment data by state-owned Perupetro, during November, the 4.4 mtpa LNG plant sent two shipments each...