Mozambique LNG restart may take another year, TotalEnergies CEO says

TotalEnergies will not restart work on its $20 billion Mozambique LNG project until the civil population comes back to the Cabo Delgado province where the Afungi site is located, according to chief executive Patrick Pouyanne.

To remind, TotalEnergies declared force majeure on the giant LNG project in April last year following new attacks, and withdrew all personnel from the site.

After that, the firm said the project would be delayed for a least one year.

Pouyanne recently visited Mozambique and met with the country’s President Filipe Jacinto Nyusi to discuss the security situation in the area where the LNG plant is located and the restart of works.

“We will not build a plant in a country surrounded by soldiers”

The CEO told analysts during the company’s quarterly results call on Thursday that, “there have been some clear improvements on the ground.”

Pouyanne said that Mozambique in partnership with SADC managed to get back the security in some key areas around Palma, where the project is located, but they “do not control today Cabo Delgado” in full.

He said that TotalEnergies would only restart the project once they take back the control of the security but also once the civil population comes back in the villages and with “a normal life.”

“That will be the signal. We will not build a plant in a country where we’ll be surrounded by soldiers. It does not work like that,” he said.

“No pressure to exit out of force majeure”

Pouyanne said he has “no idea” when the company could start working on the project again.

“Maybe it will take a year, I don’t know. We’ll see, we observe,” he said.

“There is no pressure for us to exit out of force majeure. We know that when we will say, yes, we can come back, it will take 6 months really to start up again,” he said.

“But again, my priority, it’s a matter of sustainability of that and human rights. And so we’ll not relaunch the project as long as I see photos from refugee camps around the site,” he said.

TotalEnergies had previously planned to launch the project in 2024. Mozambique LNG includes the development of offshore gas fields in Mozambique’s Area 1 and a 12.8 mtpa liquefaction plant at the Afungi complex.

The project will also have a fleet of dedicated LNG carriers.

Besides TotalEnergies, other partners in the project are Japan’s Mitsui, Mozambique’s ENH, Thailand’s PTT, and Indian firms ONGC, Bharat Petroleum, and Oil India.

The project’s EPC contractor is CCS JV, a venture between Saipem, McDermott, and Chiyoda.

Most Popular

Golar moving forward with new FLNG order

Floating LNG player Golar LNG is moving forward with its plans to order its fourth FLNG conversion. In order to secure "attractive" delivery, Golar plans to enter into slot reservations for long-lead equipment within the third quarter of this year.

AG&P LNG inks offtake MoU for Australian LNG import project

Nebula Energy’s AG&P LNG said it had signed a memorandum of understanding with an Australian integrated energy provider under which the latter may become a significant offtaker of the proposed Outer Harbor LNG terminal in South Australia.

Excelerate working to expand Jamaican LNG business

US FSRU player Excelerate Energy has already made some smaller investments to further optimize its recently acquired LNG business in Jamaica, according to CEO Steven Kobos.

More News Like This

NextDecade secures equity commitments for fourth Rio Grande LNG train

US LNG firm NextDecade has secured up to $1.8 billion in equity commitments from TotalEnergies and Global Infrastructure Partners to finance the construction of the fourth train at its Rio Grande LNG facility in Texas.

Hudong-Zhonghua to build another LNG bunkering vessel for TotalEnergies

China’s Hudong-Zhonghua said it had secured another order to build one 18,600-cbm LNG bunkering vessel for French energy giant TotalEnergies and Spain's shipping firm Ibaizabal.

TotalEnergies working on Mozambique LNG restart, CEO says

France's TotalEnergies and its partners in the giant Mozambique LNG project are still working with the Mozambique government on restarting construction on the 12.8 mtpa project, according to Patrick Pouyanne, CEO of TotalEnergies.

TotalEnergies reports higher LNG sales, lower earnings

French energy giant TotalEnergies reported higher LNG sales in the second quarter of this year, while its integrated LNG business logged lower adjusted net operating income due to lower prices.