NextDecade removes one Rio Grande LNG train in optimization move

US company NextDecade said on Monday it would ditch one train from its proposed Rio LNG export plant in Texas as part of an optimization move that includes slashing emissions.

The original design for Rio Grande LNG included six trains each capable of producing 4.5 million tonnes per year.

NextDecade believes that the LNG plant is now capable of producing the same planned total volumes with just five trains.

The LNG developer says it has during its pre-FID activities worked “diligently” to reduce the environmental impacts of the project.

The technologies that the company selected and filed with the US FERC in 2015 and 2016 “have evolved over the five-year permitting period.”

The trains are now more efficient and will produce more LNG with lower total carbon dioxide equivalent emissions.

NextDecade says it identified multiple optimizations that will lead to the delivery of the LNG project with just five trains.

The company says these will result in several “environmental and community benefits”.

These include 21 percent lower total carbon dioxide equivalent emissions and shortened construction timeline for the full 27 mtpa project.

“In addition to the emissions reductions we will achieve, these optimizations will reduce the project’s footprint, traffic, and construction schedule, and demonstrate our ongoing commitments to the community in the Rio Grande Valley,” Matt Schatzman, NextDecade’s Chairman and CEO said.

Based on these optimizations, NextDecade said it would, in due course, vacate Train 6.

The company added that future development of Train 6 would require authorization from the US FERC and other agencies.

It remains unclear when NextDecade would build the five Rio Grande trains.

The company has earlier this year postponed the final decision on the LNG export project due to the Covid-19 pandemic.

Most Popular

Greek LNG imports drop in 2024

The Greek gas grid and LNG terminal operator said Revithoussa LNG shipments in 2024 totaled 18.69 terawatt hours (TWh)...

PetroVietnam Gas seeks four LNG cargoes

According to a tender document posted on the company’s website, the cargoes will be delivered from March to May...

Thailand’s Gulf, Ratch launch second unit at Hin Kong power plant

Hin Kong Power, a joint venture owned 51 percent by Ratch and 49 percent by Gulf Energy, started the...

More News Like This

NextDecade gets $175 million loan for Rio Grande LNG

NextDecade's unit Rio Grande LNG Super has entered into a credit agreement with General Atlantic Credit's Atlantic Park Fund...

Construction progresses on NextDecade’s Rio Grande LNG project

Schatzman said in a third-quarter business update that the facility "continues to progress safely, in line with schedule, and...

NextDecade seeks Rio Grande LNG rehearing after court ruling

In August, the US Court of Appeals for the D.C. Circuit issued an order vacating the Federal Energy Regulatory...

NextDecade releases Rio Grande LNG construction update

In July 2023, NextDecade took the final investment decision on the first three Rio Grande trains and completed $18.4 billion project financing. NextDecade awarded...