NFE plans to book capacity at Gasunie’s Eemshaven LNG import terminal

US LNG player New Fortress Energy is planning to book regasification capacity at Gasunie’s new LNG import hub in the Dutch port of Eemshaven.

The new terminal with a capacity of about 8 bcm per year started delivering regasified LNG to the Dutch grid in September in record time as European countries look to slash reliance on Russian pipeline gas and boost energy security.

It consists of two chartered floating storage and regasification units or FSRUs.

The units include Exmar’s 26,000-cbm barge-based FSRU Eemshaven LNG and the 170,000-cbm Energos Igloo, previously known as Golar Igloo. A joint venture of asset manager Apollo and NFE owns Energos Igloo.

Moreover, Shell booked 4 bcm while CEZ took 3 bcm of the Eemshaven terminal’s total capacity. France’s Engie secured the remaining 1 bcm of capacity.

Now Wes Edens-led NFE is looking to book capacity at the facility on top of the FSRU charter.

“We expect the EemsEnergyTerminal to increase LNG capacity in the near-term with NFE as a potential new capacity holder of re-gas slots,” NFE said in its third-quarter results report.

The firm did not provide any additional information regarding the development in the report. NFE’s executives also did not discuss this during the third-quarter call.

A spokeswoman for Gasunie told LNG Prime that the company does not comment on market-related queries.

NFE plans to book capacity at Gasunie’s Eemshaven LNG import terminal
Image: NFE

FLNG plans

NFE plans to install floating liquefaction facilities in the US Gulf of Mexico using its “Fast LNG” liquefaction design that incorporates modular, midsize liquefaction technology with jack up rigs or similar offshore infrastructure.

It also awarded FLNG contracts to Sembcorp MarineFluorECONNECT Energy, and others.

NFE currently plans to install five floating LNG producers in the Gulf of Mexico, including off Louisiana, Altamira, and Lakach, it said in the report.

Also, the firm expects its first Fast LNG to achieve mechanical completion in March 2023 and start operations by mid-2023.

NFE expects to complete other units during 2023-2024.

“Our Fast LNG units represent more than half of the world’s expected incremental LNG supply in 2023-2024, and we expect will be utilized in the near term to address Europe’s energy security issues,” the firm said.

The company said it expects its five LNG units under development to add about 7 mtpa of new liquefaction capacity by the end of 2024 for a total LNG supply portfolio of some 9.5 mtpa.

Most Popular

Venture Global gets FERC OK to boost Plaquemines LNG capacity

US LNG exporter Venture Global LNG has received approval from the US FERC to boost the capacity of its Plaquemines LNG terminal in Louisiana to 27.2 mtpa.

Asyad Shipping sells LNG carrier

Oman's Asyad Shipping has sold a 2006-built steam liquefied natural gas (LNG) carrier, according to brokers.

First Rio Grande LNG tank taking shape

US LNG developer NextDecade continues to make progress on the first phase of its Rio Grande LNG export plant in Texas, including the first 180,000-cbm storage tank.

More News Like This

Energos to upgrade Brazilian FSRU

US-based Energos Infrastructure, controlled by asset manager Apollo, will upgrade its 170,213-cbm FSRU Energos Nanook, which works in Brazil under a charter deal.

Gasunie, Vopak to decide on Eemshaven LNG extension later this year

The Eeemshaven LNG hub consists of two chartered floating storage and regasification units – the 170,000-cbm FSRU Energos Igloo,...

NFE shipped nine Altamira LNG cargoes

According to NFE, the Fast LNG (FLNG) project is in the final phase of commissioning and is producing above...

NFE to supply gas to Puerto Rico power plant

NFE said in a statement on Wednesday that the gas supply deal is for 20 years. According to NFE, the...