PSA: Hammerfest LNG fire investigation finds Equinor broke safety rules

Norway’s Petroleum Safety Authority said it has identified regulation breaches following its investigation into a fire that broke out at Equinor’s Hammerfest LNG plant in September last year.

PSA said it has identified “serious breaches of the regulations.” The safety watchdog revealed the findings of its investigation on Thursday.

To remind, Equinor closed the 4.3 mtpa LNG plant on September 28, 2020 following a fire in turbine 4. The export facility will remain shut until October 1 as Equinor works to repair the plant.

“Technical fire tests and simulation of temperature development in the turbine’s filter housing support the likelihood that the fire broke out because pre-filters in the air intake auto-ignited,” the safety watchdog said.

“The tests indicate that biomass buildups (primarily insects) in the pre-filters may have lowered their auto-ignition temperature,” it said.

The PSA said it has sent a letter to Equinor with several orders attached.

Equinor must now ensure that “knowledge and necessary information available within the company are communicated in a systematic and appropriate manner to operations personnel,” the PSA said.

In addition, Equinor must demonstrate that the Hammerfest LNG plant has “adequate manning and competence to deal with all operating conditions.”

Hammerfest LNG liquefies natural gas coming from the Snohvit field in the Barents Sea.

Gas reaches Hammerfest LNG via a 160-kilometer gas pipeline which became operational in the autumn of 2007.

The fuel produced at the facility mainly lands at LNG terminals in Europe but also in Asia.

Equinor is the operator of both the Snohvit field and Hammerfest LNG with a 36.8 percent stake.

Most Popular

Venture Global nears launch of Plaquemines LNG production

According to a FERC filing, Plaquemines LNG has now fulfilled the environmental conditions which were necessary prior to the...

Geocean kicks off work on Congo FLNG mooring project

French marine and offshore contractor, Geocean, a VINCI Construction Grands Projets unit, has started working on a new contract...

Golar CEO says Nigerian FLNG FID unlikely before 2025

In June, Golar and NNPC signed a project development agreement (PDA) for the deployment of an FLNG. The agreement aims...

More News Like This

Equinor says costs climb for Hammerfest LNG upgrade project

The project includes onshore compression and electrification of the Hammerfest LNG terminal. "Since the PDO (plan for development and operation)...

First LNG-powered LCO2 carrier nears delivery in China

The first of two Northern Lights JV’s LNG-powered liquefied CO2 carriers is undergoing trials in China ahead of its...

Eidesvik, Equinor to convert LNG-powered PSV to use ammonia as fuel

Norwegian energy firm Equinor has signed a contract with compatriot Eidesvik Offshore to convert the LNG dual-fuel PSV, Viking...

Eidesvik’s LNG-fueled PSV to continue work with Equinor

Norwegian shipping firm Eidesvik Offshore has secured a contract extension from compatriot energy firm Equinor for one of its...