QatarEnergy and ExxonMobil progress Golden Pass LNG construction work

QatarEnergy and ExxonMobil are moving forward with the construction of their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas, in order to launch the facility in 2024.

Once complete, the giant facility located next to the existing LNG import terminal in Sabine Pass will have three trains and a total liquefaction capacity of more than 18 mtpa.

State-owned QatarEnergy owns a 70 percent stake in the project while US energy firm ExxonMobil has a 30 percent share.

QatarEnergy’s trading unit will offtake 70 percent of the Golden Pass LNG supplies and ExxonMobil will take the rest as part of a deal the two firms revealed in October last year.

QatarEnergy and ExxonMobil progress work on Golden Pass LNG export terminal
Ground flare construction (Image: Golden Pass LNG)

Construction update

A joint venture of Chiyoda, McDermott, and Zachry is building the LNG export facility worth about $10 billion.

According to the December construction update filed by Golden Pass LNG Terminal and Golden Pass Pipeline with the US FERC, “Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.”

In addition, Golden Pass has progressed installation of piping and steel in process areas and has continued walls and piping installation for the ground flares.

During December, concrete foundation pours continued in Train 2 and Train 3 and fin fan installation continued of the Train 1 main pipe rack.

Golden Pass has also started LNG tanks top modifications scope, the update said.

The construction site was closed from December 23 until January 3 for holidays observation.

As per the pipeline expansion project, Golden Pass has continued mobilization activities for the MP01 compressor station area and has continued surveying activities at the MP33 and MP69 compressor station areas, it said.

During January, Golden Pass said it would continue with construction activities described above.

Golden Pass plans to launch the first train in the first quarter of 2024, the second train in the third quarter of 2024, and the third train in the first quarter of 2025.

Most Popular

Golar’s fourth unit may be world’s largest FLNG

Golar LNG's next converted FLNG may have a capacity of 5 mtpa, which would make it the world's largest FLNG, according to CEO Karl Staubo.

Sempra eyes Port Arthur LNG expansion FID in 2025

Sempra Infrastructure, a unit of Sempra, expects to make a final investment decision on the second phase of its Port Arthur LNG export project in Texas in 2025.

Venture Global to introduce gas to 9th Plaquemines liquefaction block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the ninth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Hanwha Ocean delivers 200th LNG carrier

South Korea's Hanwha Ocean has delivered its 200th liquefied natural gas (LNG) carrier.

Sicim bags Rovuma LNG gig

Italy's Sicim has secured a contract from Subsea 7 for the ExxonMobil-led Rovuma LNG project in Mozambique.

Construction advances on Golden Pass LNG terminal

Energy giants QatarEnergy and ExxonMobil and their contractors continue to move forward with the construction work on the Golden Pass LNG export facility in Texas.

TotalEnergies CEO says partners working hard on Papua LNG

TotalEnergies has a 37.55 percent operating stake in the Papua LNG project, ExxonMobil has 37.04 percent, Santos owns a...