Saipem CFO expects Mozambique LNG work to resume next year

Italian contractor Saipem expects work on the giant $20 billion Mozambique LNG project to resume around mid-2022, according to its finance chief Antonio Paccioretti.

To remind, TotalEnergies declared force majeure on the LNG project earlier this year following new attacks near the Afungi plant site.

The project’s EPC contractor is CCS JV, a venture between Saipem, McDermott, and Chiyoda.

Paccioretti told analysts during a conference call last week that in order to reach the company’s revenues target next year “we also have to consider the contribution of Mozambique.”

As of September 30, the giant LNG project remains in Saipem’s backlog for an amount of about 3.6 billion euros ($4.15 billion), he said.

TotalEnergies said in April this year the Mozambique LNG project would be delayed for “at least one year.”

The energy giant had previously expected to launch the project in 2024. Mozambique LNG includes the development of offshore gas fields in Mozambique’s Area 1 and a 12.8 mtpa liquefaction plant at the Afungi complex.

Also, the project will have a fleet of dedicated LNG carriers.

Besides Total, other partners in the project are Japan’s Mitsui, Mozambique’s ENH, Thailand’s PTT, and Indian firms ONGC, Bharat Petroleum, and Oil India.

Most Popular

Seapeak books $19.3 million charge as it lays off seafarers on steam LNG carriers

Stonepeak’s Seapeak booked $19.3 million of restructuring charges in the second quarter of this year, primarily due to laying off its Spanish seafarers working on steam LNG carriers.

Golar moving forward with new FLNG order

Floating LNG player Golar LNG is moving forward with its plans to order its fourth FLNG conversion. In order to secure "attractive" delivery, Golar plans to enter into slot reservations for long-lead equipment within the third quarter of this year.

Hanwha’s units, Kospo to jointly buy US LNG

South Korea's Hanwha Aerospace and Hanwha Energy, units of Hanwha, are teaming up with compatriot Korea Southern Power (Kospo) to jointly buy US liquefied natural gas (LNG) supplies.

More News Like This

NextDecade secures equity commitments for fourth Rio Grande LNG train

US LNG firm NextDecade has secured up to $1.8 billion in equity commitments from TotalEnergies and Global Infrastructure Partners to finance the construction of the fourth train at its Rio Grande LNG facility in Texas.

Hudong-Zhonghua to build another LNG bunkering vessel for TotalEnergies

China’s Hudong-Zhonghua said it had secured another order to build one 18,600-cbm LNG bunkering vessel for French energy giant TotalEnergies and Spain's shipping firm Ibaizabal.

Inpex launches Abadi LNG FEED work

Japan's Inpex has launched the front-end engineering design (FEED) work for the Abadi LNG project in Indonesia. The contractors include Technip Energies, JGC, Saipem, Tripatra, McDermott, and Worley.

TotalEnergies working on Mozambique LNG restart, CEO says

France's TotalEnergies and its partners in the giant Mozambique LNG project are still working with the Mozambique government on restarting construction on the 12.8 mtpa project, according to Patrick Pouyanne, CEO of TotalEnergies.