Saipem CFO expects Mozambique LNG work to resume next year

Italian contractor Saipem expects work on the giant $20 billion Mozambique LNG project to resume around mid-2022, according to its finance chief Antonio Paccioretti.

To remind, TotalEnergies declared force majeure on the LNG project earlier this year following new attacks near the Afungi plant site.

The project’s EPC contractor is CCS JV, a venture between Saipem, McDermott, and Chiyoda.

Paccioretti told analysts during a conference call last week that in order to reach the company’s revenues target next year “we also have to consider the contribution of Mozambique.”

As of September 30, the giant LNG project remains in Saipem’s backlog for an amount of about 3.6 billion euros ($4.15 billion), he said.

TotalEnergies said in April this year the Mozambique LNG project would be delayed for “at least one year.”

The energy giant had previously expected to launch the project in 2024. Mozambique LNG includes the development of offshore gas fields in Mozambique’s Area 1 and a 12.8 mtpa liquefaction plant at the Afungi complex.

Also, the project will have a fleet of dedicated LNG carriers.

Besides Total, other partners in the project are Japan’s Mitsui, Mozambique’s ENH, Thailand’s PTT, and Indian firms ONGC, Bharat Petroleum, and Oil India.

Most Popular

Cedar LNG gets OK for capacity boost

Canada’s Cedar LNG, a joint venture of Canada’s Pembina Pipeline and the Haisla Nation, received approval to boost the capacity of its LNG project in Kitimat, on Canada’s West Coast.

Jera moving forward with Hawaii LNG plans

A unit of Japan's power firm and LNG trader, Jera, is moving forward with plans to build a $2 billion LNG-to-power project in Hawaii.

CMA CGM, Maersk eye more LNG-powered containership orders

France's CMA CGM and Denmark's Maersk are looking to order ultra-large LNG dual-fuel containerships at yards in China and South Korea, according to shipbuilding sources.
spot_img

More News Like This

UAE’s Adnoc takes FID on $6.2 billion gas project

UAE's energy giant Adnoc said on Tuesday it is accelerating its integrated global gas growth strategy with a $6.2 billion final investment decision (FID) to develop the Umm Shaif gas cap project in Abu Dhabi alongside its international partners TotalEnergies, Eni, and CNPC.

TotalEnergies places sole bid in latest Pakistan LNG tender

A unit of French energy giant TotalEnergies has submitted the only bid in a tender to supply Pakistan with one spot LNG shipment next week.

TotalEnergies expects “significantly” lower LNG results in Q2

French energy giant TotalEnergies, one of the world’s largest LNG players, expects its integrated LNG results to decrease "significantly" in the second quarter compared to the prior quarter.

Sempra Infrastructure’s ECA LNG exports first LNG cargo

US LNG exporter Sempra Infrastructure, a subsidiary of Sempra, said on Wednesday that the ECA LNG Phase 1 project in Ensenada, Mexico, has loaded and shipped its first cargo of liquefied natural gas (LNG).