Sempra secures more time to build Port Arthur LNG export plant

US LNG firm Sempra Infrastructure, a unit of Sempra, has secured a 50-month extension from US energy regulators to build its 13.5 mtpa Port Arthur liquefaction project in Texas.

US FERC approved the Port Arthur project back in April 2019 and Sempra had to complete the LNG export terminal and associated pipelines by April 2024.

Port Arthur LNG and Port Arthur Pipeline requested the extension from FERC on July 28 saying the project was impacted by the “adverse market conditions and logistical delays caused by the Covid-19 pandemic”.

“Because we find that Port Arthur has demonstrated good cause for delay and progress in developing the projects, we will grant the requested 50-month extension of time to complete construction of the Port Arthur LNG Terminal and the Louisiana Connector Project and Texas Connector Project,” FERC said in a filling dated October 13.

Following the approval, Sempra Infrastructure now has to construct and make available for service the Port Arthur LNG terminal by June 18, 2028.

The liquefaction project would consist of two liquefaction trains each capable of producing up to 6.73 mtpa. Sempra Infrastructure also plans a similarly sized second phase of the project.

Also, the first phase of the project includes three LNG storage tanks with a capacity of 160,000 cubic meters and a marine facility consisting of two berths for LNG vessels with a capacity of up to 266,000 cbm.

Sempra Infrastructure has entered into negotiations with “multiple European companies that contemplate negotiation of long-term sale and purchase agreements for LNG from the liquefaction project,” the filling said.

Earlier this year, US energy giant ConocoPhillips signed a preliminary deal with Sempra Infrastructure to buy a 30 percent direct equity holding in the project and an LNG offtake equivalent to about 5 mtpa.

Prior to this HOA, Sempra signed deals with German energy firm RWEUK’s Ineos, and Poland’s dominant gas firm and LNG importer, PGNiG, for volumes from the first phase of the LNG project.

Including this deal with ConocoPhillips, these HOAs total 9.65 mtpa to 11.65 mtpa of LNG from the first phase of the development, according to Sempra.

- Advertisements -

Most Popular

Golden Pass LNG to ramp up construction activities after Zachry deal

QatarEnergy and ExxonMobil will ramp up construction activities at the Golden Pass LNG export terminal in Texas after a...

Tellurian updates on Driftwood LNG work

US LNG terminal developer Tellurian, which is being acquired by Australia's Woodside, released the latest construction update for the...

Hudong-Zhonghua confirms TotalEnergies order for LNG bunkering vessel

China’s Hudong-Zhonghua said it had secured an order to build one 18,600-cbm LNG bunkering vessel for French energy giant...

More News Like This

Sempra, Bechtel ink EPC deal for Port Arthur LNG expansion project

US LNG exporter Sempra Infrastructure, a unit of Sempra, and compatriot engineering and construction firm Bechtel have finalized a...

Construction progresses on Sempra’s Port Arthur LNG export project

US LNG exporter Sempra and compatriot Bechtel are moving forward with construction on the first phase of the Port...

FERC approves Venture Global’s CP2 LNG project

The US FERC has given the green light to Venture Global LNG for its proposed CP2 LNG project in...

Aramco, Sempra ink non-binding Port Arthur LNG deal

Saudi Arabia’s energy behemoth Aramco has signed a non-binding deal with US LNG exporter Sempra to buy liquefied natural...