Shell says no Prelude FLNG restart before next year

The Hague-based energy giant Shell said Thursday it will not restart production at its giant Prelude FLNG facility offshore Western Australia before the next year.

Shell hasn’t exported any cargoes from the FLNG for more than nine months following an electrical trip on February 2.

“We continue to work through the process for hydrocarbon restart of Shell’s Prelude FLNG facility, with safety and stability foremost in mind,” Shell said in a statement.

“Full production is not expected to resume before year end. Prelude is a multi-decade project, and our focus is on delivering sustained performance over the long term,” the company said.

To remind, Prelude shipped its first cargo last year after several start-up delays.

The FLNG has the capacity to produce 3.6 mtpa of LNG, 1.3 mtpa of condensate and 0.4 mtpa of LPG.

Shell operates the Prelude FLNG, located 475 km from Broome in Western Australia, with a 67.5 percent stake.

Japan’s Inpex holds a 17.5 percent stake, Korea’s Kogas 10 percent, while Taiwan’s CPC holds 5 percent.

Most Popular

Three dead in accident at Port Arthur LNG site

Sempra Infrastructure and Bechtel confirmed that an incident took place on Tuesday at the Port Arthur LNG construction site in Texas, resulting in three fatalities and two injuries.

Second Wilhelmshaven FSRU arrives at jetty

Germany's Wilhelmshaven now hosts two floating storage and regasification units. Excelerate’s 138,000-cbm FSRU Excelsior has docked at a new jetty, two kilometers south of the already operational Wilhelmshaven 1 terminal, to start serving the second FSRU-based terminal.

Cheniere’s Corpus Christi expansion project 82.5 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 82.5 percent complete.

More News Like This

Venture Global launches Calcasieu Pass LNG commercial ops

US LNG exporter Venture Global LNG has launched commercial operations at its Calcasieu Pass LNG terminal in Louisiana, some 68 months from its final investment decision and 38 months after production start.

YPF expects more supermajors to join Argentina LNG project, CEO says

Argentina’s state-owned oil and gas company YPF expects more supermajors to become equity partners in the planned Argentina LNG project following a deal with Shell, according to CEO Horacio Marin.

Shell expects Q1 LNG trading results to be in line compared to previous quarter

LNG giant Shell expects trading and optimization results for its integrated gas business in the first quarter of this year to be in line compared with the fourth quarter of last year.

Peru LNG terminal sent five shipments in March

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped five liquefied natural gas cargoes in March, one more than in the previous month.