Shell’s LNG Canada almost 28 percent complete

The Shell-led LNG Canada development is moving forward despite disruptions caused by the Covid-19 pandemic. The total project progress reached about 27.5 percent, according to the main contractor Fluor.

To remind, Fluor and partner JGC hold the engineering, procurement and construction contract on the LNG export project worth more than $30 billion.

Following the FID by Shell and partners back in October 2018, the duo started working at the project site in Kitimat.

The two firms continued to perform works until March this year when they were forced to downsize the workforce by half due to the pandemic.

“In keeping with the local regulations, we had a considerable workforce reduction in mid-March, but work with the provincial governments, multi-phase reached our plant to resume activities,” Fluor chief executive Carlos Hernandez said during a recent investor call

“We’re pleased to report that our workforce is now back where it was before the drawdown, and we expect to increase it to 2,500 on-site by the end of 2020,” he said.

However, these events have caused delays within the giant LNG project.

“LNG Canada is, it is behind because of the pandemic,” Hernandez said, adding that the JV was in talks with Shell regarding the timeline.

Hernandez did not provide any additional information regarding the delays. But, according to LNG Canada, they will not affect the first LNG shipment expected in the middle of the decade.

“Works progressing well”

Despite Covid-19, works on the Kitimat site have been progressing “very well,” Hernandez said.

According to the CEO, the project is about 27.5% complete. This is on an overall basis and observed from the engineering, procurement, construction, and fabrication point of view.

“Now, obviously, that’s not construction, construction is less than that. But, we’re comfortable with the progress that has been made to date,” he said.

Shell's LNG Canada almost 28 percent complete (2)
Image: Fluor

Looking at recent milestones, the JGC Fluor team reached first concrete pour for the base of the LNG storage tank.

Once complete, the 225,000-cbm tank will be approximately 60 meters tall and 100 meters in diameter.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation and Kogas of South Korea.

LNG Canada will initially include two trains with the capacity to produce 14 million tonnes of LNG per year.

Most Popular

Venture Global’s Plaquemines LNG terminal achieves first production

Venture Global announced on Friday it had reached first LNG production at the company’s second facility, Plaquemines LNG, in...

Spot LNG rates remain weak

“Spark30S rates rose for a fourth consecutive week, increasing marginally by $750 to $23,500 per day,” Qasim Afghan, Spark’s commercial...

Swan Energy, Nebula’s AG&P LNG plan Indian JV

Swan Energy said on Friday it had signed a heads of agreement with AG&P Terminals &Logistics (Singapore). The two firms...

More News Like This

YPF, Shell seal Argentina LNG deal

YPF president and CEO Horacio Marin, and Shell's executive VP of LNG, Cederic Cremers,signed the deal in The Hague,...

Chevron-led JV secures GHG permit near Barrow Island

US energy giant Chevron and its partners Shell and ExxonMobil have been awarded the greenhouse gas (GHG) assessment permit...

Shell’s LNG Canada names new CEO

Cooper, currently LNG Canada’s senior vice president for Phase 1 pipeline and expansion will succeed Jason Klein as president...

Peru LNG terminal sent six cargoes in November

According to the shipment data by state-owned Perupetro, during November, the 4.4 mtpa LNG plant sent two shipments each...