Shell’s LNG Canada almost 28 percent complete

The Shell-led LNG Canada development is moving forward despite disruptions caused by the Covid-19 pandemic. The total project progress reached about 27.5 percent, according to the main contractor Fluor.

To remind, Fluor and partner JGC hold the engineering, procurement and construction contract on the LNG export project worth more than $30 billion.

Following the FID by Shell and partners back in October 2018, the duo started working at the project site in Kitimat.

The two firms continued to perform works until March this year when they were forced to downsize the workforce by half due to the pandemic.

“In keeping with the local regulations, we had a considerable workforce reduction in mid-March, but work with the provincial governments, multi-phase reached our plant to resume activities,” Fluor chief executive Carlos Hernandez said during a recent investor call

“We’re pleased to report that our workforce is now back where it was before the drawdown, and we expect to increase it to 2,500 on-site by the end of 2020,” he said.

However, these events have caused delays within the giant LNG project.

“LNG Canada is, it is behind because of the pandemic,” Hernandez said, adding that the JV was in talks with Shell regarding the timeline.

Hernandez did not provide any additional information regarding the delays. But, according to LNG Canada, they will not affect the first LNG shipment expected in the middle of the decade.

“Works progressing well”

Despite Covid-19, works on the Kitimat site have been progressing “very well,” Hernandez said.

According to the CEO, the project is about 27.5% complete. This is on an overall basis and observed from the engineering, procurement, construction, and fabrication point of view.

“Now, obviously, that’s not construction, construction is less than that. But, we’re comfortable with the progress that has been made to date,” he said.

Shell's LNG Canada almost 28 percent complete (2)
Image: Fluor

Looking at recent milestones, the JGC Fluor team reached first concrete pour for the base of the LNG storage tank.

Once complete, the 225,000-cbm tank will be approximately 60 meters tall and 100 meters in diameter.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation and Kogas of South Korea.

LNG Canada will initially include two trains with the capacity to produce 14 million tonnes of LNG per year.

Most Popular

Excelerate in $700 million senior notes offering

US FSRU player Excelerate Energy aims to raise about $700 million via an offering of unsecured senior notes due 2030.

Adnoc, ENN seal 15-year LNG SPA

UAE’s Adnoc has signed a 15-year sales and purchase agreement with Chinese independent gas distributor ENN to supply the latter with LNG from its LNG terminal in Al Ruwais.

LNG shipping rates continue to decrease

Spot LNG freight shipping rates in both basins continued to decrease this week, while European prices increased compared to last week.

More News Like This

Venture Global launches Calcasieu Pass LNG commercial ops

US LNG exporter Venture Global LNG has launched commercial operations at its Calcasieu Pass LNG terminal in Louisiana, some 68 months from its final investment decision and 38 months after production start.

YPF expects more supermajors to join Argentina LNG project, CEO says

Argentina’s state-owned oil and gas company YPF expects more supermajors to become equity partners in the planned Argentina LNG project following a deal with Shell, according to CEO Horacio Marin.

Shell expects Q1 LNG trading results to be in line compared to previous quarter

LNG giant Shell expects trading and optimization results for its integrated gas business in the first quarter of this year to be in line compared with the fourth quarter of last year.

Peru LNG terminal sent five shipments in March

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped five liquefied natural gas cargoes in March, one more than in the previous month.