Shell’s LNG Canada almost 28 percent complete

The Shell-led LNG Canada development is moving forward despite disruptions caused by the Covid-19 pandemic. The total project progress reached about 27.5 percent, according to the main contractor Fluor.

To remind, Fluor and partner JGC hold the engineering, procurement and construction contract on the LNG export project worth more than $30 billion.

Following the FID by Shell and partners back in October 2018, the duo started working at the project site in Kitimat.

The two firms continued to perform works until March this year when they were forced to downsize the workforce by half due to the pandemic.

“In keeping with the local regulations, we had a considerable workforce reduction in mid-March, but work with the provincial governments, multi-phase reached our plant to resume activities,” Fluor chief executive Carlos Hernandez said during a recent investor call

“We’re pleased to report that our workforce is now back where it was before the drawdown, and we expect to increase it to 2,500 on-site by the end of 2020,” he said.

However, these events have caused delays within the giant LNG project.

“LNG Canada is, it is behind because of the pandemic,” Hernandez said, adding that the JV was in talks with Shell regarding the timeline.

Hernandez did not provide any additional information regarding the delays. But, according to LNG Canada, they will not affect the first LNG shipment expected in the middle of the decade.

“Works progressing well”

Despite Covid-19, works on the Kitimat site have been progressing “very well,” Hernandez said.

According to the CEO, the project is about 27.5% complete. This is on an overall basis and observed from the engineering, procurement, construction, and fabrication point of view.

“Now, obviously, that’s not construction, construction is less than that. But, we’re comfortable with the progress that has been made to date,” he said.

Shell's LNG Canada almost 28 percent complete (2)
Image: Fluor

Looking at recent milestones, the JGC Fluor team reached first concrete pour for the base of the LNG storage tank.

Once complete, the 225,000-cbm tank will be approximately 60 meters tall and 100 meters in diameter.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation and Kogas of South Korea.

LNG Canada will initially include two trains with the capacity to produce 14 million tonnes of LNG per year.

- Advertisements -

Most Popular

ExxonMobil working on larger Rovuma LNG export project in Mozambique

US energy giant ExxonMobil has boosted the capacity of the planned Rovuma LNG onshore terminal in Mozambique and is...

Sempra takes FID on Port Arthur LNG project

US LNG player Sempra Infrastructure, a unit of Sempra, has taken a final investment decision for the first phase...

Excelerate to buy FSRU from Maran Gas

US floating LNG player Excelerate Energy plans to exercise an option to buy the 2020-built FSRU Sequoia from Greece’s...

More News Like This

Mexico Pacific seals another LNG supply deal with Shell

A unit of LNG giant Shell has signed another long-term deal to buy liquefied natural gas from Mexico Pacific,...

EnerMech clinches Canadian LNG gig

A unit of EnerMech has secured a contract to deliver its mechanical pre-commissioning and commissioning services to a large...

India’s GAIL and Shell ink LNG pact

India’s largest gas utility GAIL and LNG giant Shell are joining forces to collaborate in various fields, including LNG...

JGC, Hyundai E&C score Papua LNG gig

Japan's JGC and South Korea's Hyundai Engineering & Construction have secured a contract for the Papua LNG project in...