TC Energy says LNG Canada pipeline 84 percent complete, evaluates second phase

TC Energy said that its Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada export terminal, is 84 percent complete while the firm is also evaluating the second phase of the project.

Earlier this month, the Canadian firm revealed it now estimates costs for the first phase of its giant 670 kilometers long pipeline to reach C$14.5 billion ($10.9 billion).

If the construction continues into 2024, costs would further increase by up to C$1.2 billion.

TC Energy said in its 2022 results report on Thursday that Coastal GasLink project has now reached 84 percent overall progress, and the firm still expects mechanical completion by the end of 2023.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

As per the LNG Canada plant in Kitimat, the C$40 billion project is 80 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides the first phase, Shell and its partners Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas are also looking to build the second phase of the project.

This includes the development of the second phase of the Coastal GasLink pipeline as well.

Bevin Wirzba, TC Energy’s head of corporate development told analysts during the results call on Tuesday that “LNG Canada is developing not only their first trains, but they’ve asked us to begin the evaluation of Phase 2.”

“We’re very excited to be contemplating the expansion of our system that would not be a linear development. It’s the addition of six compressor station sites, which we’ve demonstrated at Wilde Lake that we’ve just brought to mechanically complete,” he said.

“Project economics, those are obviously confidential, but we’re encouraged by the possibility of advancing to an FID stage,” Wirzba said.

He also mentioned the Cedar LNG project, a joint venture of Pembina Pipeline and the Haisla Nation.

This proposed $2.4 billion floating LNG export facility in Kitimat, British Columbia is looking to receive feed gas from the Coastal GasLink pipeline as well.

“The other project, in addition to Phase 2, that’s important to note is the Haisla-led Cedar LNG project, which would be the largest single indigenous lead investment in Canada’s history. So we’re working with them as a customer as well as an offtaker off of CGL,” Wirzba said.

Most Popular

Venture Global LNG gets Calcasieu Pass approval from FERC

US LNG exporter Venture Global LNG has received approval from the US FERC to launch operations of its entire Calcasieu Pass LNG terminal in Louisiana.

Glencore seals LNG supply deal with China’s Shandong Order Group

China’s Shandong Order Group has signed a deal to buy liquefied natural gas (LNG) from a unit of Switzerland-based energy trader Glencore.

HD Hyundai Samho clinches $262 million LNG carrier order

South Korea’s HD Hyundai Samho has secured an order to build one liquefied natural gas (LNG) carrier for about $262 million.

More News Like This

Chris Cooper takes over as LNG Canada CEO

Chris Cooper has taken over as president and chief executive officer of LNG Canada as the Shell-led JV prepares to ship the first LNG cargoes from the Kitimat facility.

Update: Shell’s LNG Canada receives LNG cargo

Shell’s LNG Canada has received a cargo of liquefied natural gas as part of the commissioning and start-up phase.

Cedar LNG gets $140 million boost from Canada

Canada’s Pembina Pipeline and the Haisla Nation have received up to C$200 million ($140 million) from the government of Canada for their $4 billion Cedar LNG project.

Shell’s LNG Canada set to receive LNG cargo as part of commissioning activities

Shell’s LNG Canada is set to receive a cargo of liquefied natural gas onboard the 173,400-cbm LNG carrier, Maran Gas Roxana, as part of the commissioning and start-up phase, a spokesman for LNG Canada told LNG Prime.